S 0.140 +0.0% BNKR 4.40 −2.2% QRO 0.045 +0.0% VCT 0.075 +36.4% PPP 1.15 +0.9% LMG 0.390 +0.0% GRDM 0.140 +0.0% ABRA 13.58 −4.1% WHY 0.295 +1.7% HHH 3.94 −0.2% COS 0.060 +0.0% NOB 0.065 −23.5% MEK 0.055 +0.0% TGOL 0.105 −4.5% FCI 0.400 −7.0% SGQ 0.350 +0.0% S 0.140 +0.0% BNKR 4.40 −2.2% QRO 0.045 +0.0% VCT 0.075 +36.4% PPP 1.15 +0.9% LMG 0.390 +0.0% GRDM 0.140 +0.0% ABRA 13.58 −4.1% WHY 0.295 +1.7% HHH 3.94 −0.2% COS 0.060 +0.0% NOB 0.065 −23.5% MEK 0.055 +0.0% TGOL 0.105 −4.5% FCI 0.400 −7.0% SGQ 0.350 +0.0%
Production / Operations

Cornish Metals continues NCK dewatering, refurbishment

CUSN · Price

Executive Summary

  • Cornish Metals reports that dewatering and refurbishment of the New Cook’s Kitchen (NCK) shaft have reached the mid‑shaft pump station (~360 m depth).
  • Installation of new permanent pumps at the mid‑shaft station has begun, with work expected to finish in Q4 2025.
  • After completion, submersible pumps will be lowered to the lower pump station (~730 m) and dewatering/refurbishment is projected to resume, targeting mid‑2026 for completion to that level.

Key Details

  • Current Progress: Mid‑shaft pump station at ~360 m below surface secured; underground chamber stabilized; new permanent pumps being installed.
  • Depth Targets: Submersible pumps presently operating at ~380 m; lower pump station planned at ~730 m.
  • Timeline: Mid‑shaft work to be completed in Q4 2025; subsequent dewatering and shaft refurbishment to the lower level expected by mid‑2026, consistent with prior guidance (July 23 2025 update).
  • Operational Impact: Continued parallel progress of shaft refurbishment and mine dewatering ensures alignment with project schedule for South Crofty tin development.

Notable Quotes

(No direct quotes provided in the release.)