S 0.140 +0.0% BNKR 4.40 −2.2% QRO 0.045 +0.0% VCT 0.075 +36.4% PPP 1.15 +0.9% LMG 0.390 +0.0% GRDM 0.140 +0.0% ABRA 13.58 −4.1% WHY 0.295 +1.7% HHH 3.94 −0.2% COS 0.060 +0.0% NOB 0.065 −23.5% MEK 0.055 +0.0% TGOL 0.105 −4.5% FCI 0.400 −7.0% SGQ 0.350 +0.0% S 0.140 +0.0% BNKR 4.40 −2.2% QRO 0.045 +0.0% VCT 0.075 +36.4% PPP 1.15 +0.9% LMG 0.390 +0.0% GRDM 0.140 +0.0% ABRA 13.58 −4.1% WHY 0.295 +1.7% HHH 3.94 −0.2% COS 0.060 +0.0% NOB 0.065 −23.5% MEK 0.055 +0.0% TGOL 0.105 −4.5% FCI 0.400 −7.0% SGQ 0.350 +0.0%
Production / Operations

Ivanhoe Mines set to start stage 2 dewatering at Kakula

IVN · Price

Executive Summary

  • Stage 2 dewatering of the Kakula mine has begun, with four high‑capacity submersible pumps (650 L/s each) being installed and two already in place, targeting completion by end‑November 2025.
  • Completion of stage 2 will enable re‑access to western high‑grade zones within eight weeks and allow selective mining on the eastern side in Q1 2026, improving copper grades toward year‑end.
  • Ivanhoe Mines will release its 2026–2027 copper production guidance in September 2025 and a life‑of‑mine plan in late Q1 2026; refurbishment of Inga II turbine No. 5 is entering pre‑commissioning with expected completion early Q4 2025.

Key Details

  • Stage 2 Dewatering Scope: Installation of four 4.2 MW submersible pumps (650 L/s each) in two existing 400 m shafts on the eastern side of Kakula; powered by a dedicated 20 MW generator.
  • Pump Delivery & Installation: Four of five ordered pumps from Hefei Hengda Jianghai Pump Co. have been delivered; two installed as of Aug 15, with the remaining two expected operational mid‑September 2025.
  • Timeline: Pumps to remain fully submerged until end‑November 2025 when water levels are expected near the bottom of stage 2 shafts.
  • Western Side Dewatering: Expected completion within eight weeks; no seismic activity recorded, allowing rapid re‑access to high‑grade zones.
  • Rehabilitation Status: Underground rehabilitation up to current water levels is complete; stage 1 temporary pumping infrastructure will be redeployed to support stage 2.
  • Future Mining Plans: Selective mining on the eastern side anticipated in Q1 2026 once water recedes.
  • Stage 3 Dewatering: Planned for late 2025, involving rehabilitation and recommissioning of existing pump stations on the eastern side; will be the final dewatering stage using horizontal pumping infrastructure.
  • Production Guidance Release: 2026‑2027 copper production guidance slated for mid‑late September 2025; life‑of‑mine plan to follow in late Q1 2026.
  • Inga II Hydro Refurbishment: Mechanical and electrical installation of turbine No. 5 completed; pre‑commissioning underway with full commissioning expected early Q4 2025.
  • Technical Review: Technical disclosures approved by qualified persons Steve Amos (EVP, Projects) and Joshua Chitambala (Resource Manager) under NI 43‑101.