SSR Mining Announces Results of the Hod Maden Technical Report Summary With $1.66B NPV5% and 39% IRR

Executive Summary
- SSR Mining released the 2025 Hod Maden Technical Report Summary, projecting an after‑tax NPV₅% of $1.66 billion and a 39% IRR at consensus metal prices.
- Total remaining development capital is estimated at $910 million (including $75 m sustaining capex and $14 m reclamation), with SSR’s expected additional investment of ~$469 million to reach its 40% ownership stake.
- The project is forecast to generate average annual after‑tax operating cash flow of $343 million and free cash flow of $328 million (SSR attributable $131 million) at consensus prices, rising to $511 m/$496 m respectively at spot metal prices.
Key Details
- Project Economics (Consensus Prices)
- After‑tax NPV₅%: $1.66 billion
- IRR: 39%
- Average annual operating cash flow: $343 million
-
Average annual free cash flow: $328 million (SSR attributable $131 million)
-
Project Economics (Spot Prices)
- After‑tax NPV₅%: $2.91 billion
- IRR: 58%
-
Avg. operating cash flow: $511 million
Avg. free cash flow: $496 million** -
Life‑of‑Mine Production (2025‑2038)
- Gold: 1,609 koz (avg. 159 koz/yr)
- Copper: 209 Mlb (avg. 21 Mlb/yr)
-
Gold equivalent: 1,909 koz
-
Cost Structure (per payable ounce of gold)
- Cost of sales: $1,120
- Cash costs: $535
-
All‑In Sustaining Costs (AISC): $590
-
Capital Requirements
- Total development capital (remaining): $910 million
- Underground mine development: $77 m (8%)
- Process facility: $84 m (9%)
- Site & regional infrastructure: $304 m (33%)
- EPCM, site support & other: $189 m (21%)
- Contingency: $106 m (12%)
- Inflation escalation allowance: $150 m (16%)
- Sustaining capital (annual): $75 million
-
Reclamation provision: $14 million
-
SSR Mining’s Expected Additional Investment
-
Total additional spend to reach 40% ownership: ≈ $469 million
- $364 m for attributable development capex (40% of $910 m)
- $105 m in earn‑in and milestone payments
-
Operating Metrics
- Mining rate: ~2,200 t/d (800 k t/yr)
- Average ore grades: 7.6 g/t Au, 1.3% Cu
- Gold recovery: 87%, Copper recovery: 97%
-
Process plant design capacity: 800 k t/yr, single copper‑gold concentrate (22% Cu, 113 g/t Au)
-
Reserves & Resources (as of 31 Aug 2025)
- Proven + Probable reserves: 7,714 kt containing 1,896 koz Au and 223 Mlb Cu
- Measured + Indicated resources: 1,722 kt (658 koz Au, 65 Mlb Cu)
-
Inferred resources: 2,574 kt (281 koz Au, 26 Mlb Cu)
-
Key Project Milestones & Outlook
- Detailed engineering ~85% complete; major contracts tendered or awarded.
- Permit milestones: paste‑fill permit expected 2027; all private land expropriation completed.
-
Decision point anticipated in 2026 pending JV partner approvals.
-
Sensitivity Analyses (NPV₅% & IRR)
- Gold price –30% → NPV $852 m, IRR 24.3%; +30% → NPV $2,427 m, IRR 51.6%.
-
Development capex ±5‑30% shows NPV ranging $1.447‑$1.692 billion; IRR 29.1‑41.2%.
-
Forward‑Looking Statements – The release contains extensive forward‑looking information regarding production, costs, capital needs, permitting and market assumptions.
Notable Quotes
“This is a major milestone for our Company and clearly reaffirms Hod Maden’s position amongst the most compelling undeveloped copper‑gold projects globally.” – Rod Antal, Executive Chairman, SSR Mining.
All non‑material boilerplate, safe‑harbor language and contact information have been omitted.