Capstone Copper's Mantoverde operates at half-capacity

CS · Price
Executive Summary
- Capstone Copper reports a motor failure in both ball‑mill drives at the Mantoverde mine, reducing production to roughly half capacity.
- Repairs are expected to take about four weeks; the company estimates a loss of 3,000–4,000 tonnes of copper concentrate during this period.
- Mitigation plans include rescheduling planned plant maintenance and operating the circuit in bypass mode, which has been used previously.
Key Details
- Failure timeline: First ball‑mill drive motor failed on Aug 24; second drive motor failed on Aug 30.
- Repair estimate: Approximately four weeks to replace/repair the damaged motors.
- Production impact: Expected reduction of 3,000–4,000 tonnes of copper in concentrate over the repair period.
- Operating mode: Mantoverde will run at ~50 % capacity by bypassing the ball mill; this configuration is pre‑approved and has been executed before.
- Mitigation actions:
- Replacement of the first failed motor with a spare part.
- Evaluation of rescheduling September plant maintenance to align with downtime.
- Ongoing root‑cause investigation and development of a replacement strategy for the second motor.
- Future updates: Capstone will provide additional information as the situation evolves.