S 0.140 +0.0% BNKR 4.40 −2.2% QRO 0.045 +0.0% VCT 0.075 +36.4% PPP 1.15 +0.9% LMG 0.390 +0.0% GRDM 0.140 +0.0% ABRA 13.58 −4.1% WHY 0.295 +1.7% HHH 3.94 −0.2% COS 0.060 +0.0% NOB 0.065 −23.5% MEK 0.055 +0.0% TGOL 0.105 −4.5% FCI 0.400 −7.0% SGQ 0.350 +0.0% S 0.140 +0.0% BNKR 4.40 −2.2% QRO 0.045 +0.0% VCT 0.075 +36.4% PPP 1.15 +0.9% LMG 0.390 +0.0% GRDM 0.140 +0.0% ABRA 13.58 −4.1% WHY 0.295 +1.7% HHH 3.94 −0.2% COS 0.060 +0.0% NOB 0.065 −23.5% MEK 0.055 +0.0% TGOL 0.105 −4.5% FCI 0.400 −7.0% SGQ 0.350 +0.0%
Production / Operations

E3 Lithium begins commissioning at Clearwater demo site

ETL · Price

Executive Summary

  • E3 Lithium began commissioning Phase 1 of its Clearwater Project demonstration facility, targeting full operation of the 30‑column DLE system and purification equipment.
  • Initial brine feed into the DLE system was completed; a one‑week commissioning period is expected before lithium chloride production begins.
  • Sufficient on‑site brine reserves will support Phase 1 operations into early Q4 2025, with results to be reported as they become available.

Key Details

  • Phase 1 Scope: Operate 30‑column Direct Lithium Extraction (DLE) system and downstream polishing/purification units to produce high‑purity lithium chloride for conversion to battery‑grade lithium carbonate.
  • Commissioning Timeline:
  • Final testing & operational reviews completed late last week.
  • Brine introduction into DLE system occurred over the past weekend.
  • Expected one‑week period to fully commission DLE system, followed by initialization of purification units.
  • Operational Goal: Validate equipment functionality under real‑time conditions and generate high‑quality lithium chloride as a feedstock for carbonate production.
  • Brine Supply: On‑site brine inventory sufficient to run Phase 1 DLE and purification units into early Q4 2025.
  • Future Plans: Upon successful completion of Phase 1, the facility will transition to full operations; Phase 2 commissioning is slated to begin later in the fall.
  • Management Quote: Chris Doornbos, President & CEO, stated that Phase 1 commissioning “highlights the equipment is in full working order and is an exciting next step…”.

Notable Quotes

"The commissioning of phase 1 of our demonstration facility highlights the equipment is in full working order and is an exciting next step for the advancement of this facility," – Chris Doornbos, President & CEO.


Materiality Assessment: Material – Positive (demonstrates progress toward commercial production and de‑risking of the project).