Northwire Canada EditionSaturday, August 1, 2026
Northwire
S 0.140 +0.0% BNKR 4.40 −2.2% QRO 0.045 +0.0% VCT 0.075 +36.4% PPP 1.15 +0.9% LMG 0.390 +0.0% GRDM 0.140 +0.0% ABRA 13.58 −4.1% WHY 0.295 +1.7% HHH 3.94 −0.2% COS 0.060 +0.0% NOB 0.065 −23.5% MEK 0.055 +0.0% TGOL 0.105 −4.5% FCI 0.400 −7.0% SGQ 0.350 +0.0% S 0.140 +0.0% BNKR 4.40 −2.2% QRO 0.045 +0.0% VCT 0.075 +36.4% PPP 1.15 +0.9% LMG 0.390 +0.0% GRDM 0.140 +0.0% ABRA 13.58 −4.1% WHY 0.295 +1.7% HHH 3.94 −0.2% COS 0.060 +0.0% NOB 0.065 −23.5% MEK 0.055 +0.0% TGOL 0.105 −4.5% FCI 0.400 −7.0% SGQ 0.350 +0.0%
Production / Operations

Dynacor resumes ore supply to mill

DNG · Price

Executive Summary

  • Dynacor reports that ore feed to its mill has resumed at full capacity following the removal of road blockades in July.
  • Construction of a pilot plant in Senegal is on schedule, with modular equipment delivery expected in Q4 2026 and first ore processing targeted for Q1 2026.
  • The company signed a share purchase agreement for the Svetlana processing plant in Ecuador and is advancing corporate structuring, plant upgrades, and stakeholder engagement there.

Key Details

  • Mill Operations: Road blockades lifted mid‑July; ore supply resumed; mill operating at full capacity; ongoing mill‑optimization projects have begun reducing reagent use, water consumption, and improving laboratory and tailings‑pond efficiency.
  • Senegal Pilot Plant: Construction team mobilized on site; three‑km access road, land clearance, and fencing to start after September rains; tailings‑pond construction slated for end of September; modular pilot plant delivery expected Q4 2026; first ore processing targeted Q1 2026.
  • Ecuador – Svetlana Plant Acquisition: Share purchase agreement signed in July 2026; corporate structure (banking, legal, fiscal) being established with Ecuadorian authorities; negotiations underway for an Investment Protection Agreement (IPA) with MPCEIP.
  • Plant Upgrade Plans (Ecuador): Scope of work for RFQs progressing; immediate priorities include assessment and safe de‑commissioning of two historic tailings ponds to international standards; electrical substation overview being prepared to support large motor commissioning; majority of plant personnel retained for knowledge transfer.
  • Stakeholder Engagement (Ecuador): After government approval, social participation process for supplemental environmental impact study will commence; community outreach planned to explain environmental management and community‑relations program.
  • Ghana: Ongoing discussions with GoldBod, Ghana’s Ministry of Lands and Natural Resources, and the Minerals Commission regarding a business plan following productive July meetings.
  • Ivory Coast: Monitoring revisions to the mining code; no decision expected before October 2026 presidential election.
  • Financial Outlook: Company remains on schedule to generate > US$1 billion in sales by 2030.

Notable Quotes

(No direct quotes were provided in the release.)

Read the original news release →