S 0.140 +0.0% BNKR 4.40 −2.2% QRO 0.045 +0.0% VCT 0.075 +36.4% PPP 1.15 +0.9% LMG 0.390 +0.0% GRDM 0.140 +0.0% ABRA 13.58 −4.1% WHY 0.295 +1.7% HHH 3.94 −0.2% COS 0.060 +0.0% NOB 0.065 −23.5% MEK 0.055 +0.0% TGOL 0.105 −4.5% FCI 0.400 −7.0% SGQ 0.350 +0.0% S 0.140 +0.0% BNKR 4.40 −2.2% QRO 0.045 +0.0% VCT 0.075 +36.4% PPP 1.15 +0.9% LMG 0.390 +0.0% GRDM 0.140 +0.0% ABRA 13.58 −4.1% WHY 0.295 +1.7% HHH 3.94 −0.2% COS 0.060 +0.0% NOB 0.065 −23.5% MEK 0.055 +0.0% TGOL 0.105 −4.5% FCI 0.400 −7.0% SGQ 0.350 +0.0%
Production / Operations

Ecora notes Vale's Sept. 4 NR about Voisey's Bay test

ECOR · Price

Executive Summary

  • Ecora Resources notes Vale Base Metals’ completion of a cobalt throughput test at the Voisey’s Bay mine, achieving an average throughput rate of 93.7 % over a 90‑day period.
  • The result confirms the viability of the cobalt stream to which Ecora holds a 70 % net interest and entitlement to 22.82 % of production until 7,600 t of finished cobalt are delivered (11.41 % thereafter).
  • The positive test supports Ecora’s exposure to critical‑metal royalties and streams aligned with its electrification‑focused strategy.

Key Details

  • Vale Base Metals announced on Sept. 4 that the Voisey’s Bay cobalt throughput test was completed successfully.
  • Average throughput rate recorded: 93.7 % over a 90‑day testing period.
  • Ecora holds a 70 % net interest in the cobalt stream from Voisey’s Bay.
  • Entitlement structure: 22.82 % of all cobalt production until 7,600 t of finished cobalt are delivered; thereafter 11.41 % entitlement.
  • The test outcome validates the operational performance of the mine’s cobalt processing facilities, reinforcing Ecora’s exposure to a high‑grade critical mineral asset.