S 0.140 +0.0% BNKR 4.40 −2.2% QRO 0.045 +0.0% VCT 0.075 +36.4% PPP 1.15 +0.9% LMG 0.390 +0.0% GRDM 0.140 +0.0% ABRA 13.58 −4.1% WHY 0.295 +1.7% HHH 3.94 −0.2% COS 0.060 +0.0% NOB 0.065 −23.5% MEK 0.055 +0.0% TGOL 0.105 −4.5% FCI 0.400 −7.0% SGQ 0.350 +0.0% S 0.140 +0.0% BNKR 4.40 −2.2% QRO 0.045 +0.0% VCT 0.075 +36.4% PPP 1.15 +0.9% LMG 0.390 +0.0% GRDM 0.140 +0.0% ABRA 13.58 −4.1% WHY 0.295 +1.7% HHH 3.94 −0.2% COS 0.060 +0.0% NOB 0.065 −23.5% MEK 0.055 +0.0% TGOL 0.105 −4.5% FCI 0.400 −7.0% SGQ 0.350 +0.0%
Production / Operations

Abcourt to boost Sleeping Giant underground development

ABI · Price

Executive Summary

  • Abcourt Mines reports progress on the Sleeping Giant project, including commissioning of the crushing and grinding circuit and completion of a 50‑room camp.
  • The company outlines an August 2025 work plan to ready the mill for gold dore production and a September 2025 outlook targeting 5,000–10,000 t/month ore throughput and the start of gold dore pouring.
  • A board amendment changes the exercise price of previously granted stock options from $0.07 to $0.08 per share.

Key Details

  • Mill Ramp‑Up: Mill circuit now has a full inventory; plan to operate 40 h/week at 30 t/h, then increase to 80 h/week at the same rate.
  • Gold Production Goal: Target of 30,000 oz of gold annually once steady‑state operations are achieved.
  • August 2025 Activities:
  • Commission crushing and grinding circuit.
  • Fill leach circuit tanks.
  • Complete 50‑room camp and kitchen installation.
  • Begin using tailings facility for pulp storage.
  • Hire miners for seven‑day, two‑shift underground operation.
  • September 2025 Outlook:
  • Underground development to reach 5,000 t/month ore production, moving toward a steady state of 10,000 t/month as per the 2023 PEA.
  • Commence pouring gold dore.
  • Request construction permit to expand camp capacity from 50 to 100 rooms.
  • Increase underground diamond drilling rigs from two to three.
  • Stock Option Exercise Price Amendment: Board approved raising the exercise price of 21.6 million common share purchase options to $0.08 per share (previously $0.07).
  • Conference Attendance: Abcourt will present at Mining Forum Americas 2025, Sept 14‑17, Colorado Springs, CO.

Notable Quotes

“We are progressing very well with the project by now having the mill circuit with a full inventory… The next phase … will be to start delivering gold bars to the market in a high gold priced environment.” – Pascal Hamelin, President & CEO


Qualified Person: Pascal Hamelin, Eng., qualified under NI 43‑101.

Read the original news release →