B2Gold reduces Goose 2025 gold production guidance

Executive Summary
- B2Gold confirms 2025 consolidated gold production guidance of 970,000 – 1,075,000 ounces.
- Updated mine‑specific 2025 production guidance: Goose (80k–110k oz, down), Fekola (515k–550k oz, unchanged), Otjikoto (185k–205k oz, up) and Masbate (190k–210k oz, up).
- Announces progress on Goose commissioning, underground start‑up at Fekola, Antelope underground development at Otjikoto, and continued strong performance at Masbate.
Key Details
- Goose Mine (Canada) – First gold pour on June 30 2025; mill operating at ~75% of 4,000 t/d design capacity; commercial production expected in coming weeks.
- Revised 2025 guidance: 80,000–110,000 oz (previously 120,000–150,000 oz).
- Q4‑2025 production still expected at ~70,000 oz.
- Long‑term forecasts: ≈250k oz in 2026, ≈330k oz in 2027; average ≈300k oz/yr (2026‑2031).
-
Ongoing optimization studies (flotation/concentrate leach, potential SAG mill) to be finalized late 2025.
-
Fekola Complex (Mali) – State of Mali approved underground operations on July 30 2025; stope ore now processed through mill with positive grade reconciliations.
- Anticipated receipt of Regional exploitation permit by end Q3 2025; pre‑stripping to begin thereafter, with first regional production expected early 2026.
- Revised 2025 guidance unchanged: 515,000–550,000 oz.
- Underground contribution revised to 30,000–40,000 oz (up from 25k–35k).
-
Open‑pit (Fekola + Cardinal) contribution: 485,000–510,000 oz (up from 470k–490k).
-
Otjikoto Mine (Namibia) – Exceeded ore tonnage and grade expectations in final pit phases; stockpiles larger than anticipated.
- Revised 2025 guidance: 185,000–205,000 oz (previously 165k–185k oz).
- Development decision approved for Antelope underground deposit; pre‑production capital cost reduced to $105 million (down from $129 million).
-
Antelope could add ~110,000 oz/yr once in production (2026‑2027 capital spend).
-
Masbate Mine (Philippines) – Continued outperformance into Q3 2025; mill throughput above plan, grade and recovery on target.
-
Revised 2025 guidance: 190,000–210,000 oz (previously 170k–190k oz).
-
Consolidated Guidance – Company reiterates full‑year 2025 gold production range of 970,000 – 1,075,000 ounces.
Notable Quotes
(No direct quotes were provided in the release.)