TLO 5.92 +11.5% ADE 0.135 +0.0% FAIR 0.055 +22.2% SVRS 0.425 −1.2% RES 0.035 +0.0% CYG 0.120 +0.0% MGG 0.315 −4.5% BUFF 0.770 +2.7% TKO 11.25 +12.9% MINK 0.100 −4.8% LCE 0.240 −4.0% AEF 0.165 +3.1% BEM 0.095 +5.6% APMI 0.120 +0.0% LIO 0.135 +3.9% TLO 5.92 +11.5% ADE 0.135 +0.0% FAIR 0.055 +22.2% SVRS 0.425 −1.2% RES 0.035 +0.0% CYG 0.120 +0.0% MGG 0.315 −4.5% BUFF 0.770 +2.7% TKO 11.25 +12.9% MINK 0.100 −4.8% LCE 0.240 −4.0% AEF 0.165 +3.1% BEM 0.095 +5.6% APMI 0.120 +0.0% LIO 0.135 +3.9%
Drill Results

Pulsar Helium Reports Completion of Jetstream #7 and Commencement of Down-Hole Logging at the Topaz Helium Project, USA

PLSR · Price

Executive Summary

  • Pulsar Helium completed drilling of Jetstream #7 appraisal well at the Topaz Helium Project, reaching a total depth of 2,979 ft (908 m).
  • The well intersected pressurized gas at ~2,107 ft (642 m) with a preliminary bottom‑hole pressure of ~953 psi and visible gas influx, maintaining a 100% success rate across all seven Jetstream appraisal wells.
  • Down‑hole logging of Jetstream #7 is finished; flow and pressure build‑up testing for the Jetstream wells is slated to begin in late March/early April 2026.

Key Details

  • Drilling Completion: Jetstream #7 reached TD = 2,979 ft (908 m) on 10 Mar 2026; drilling campaign now concluded.
  • Gas Encounter: Gas hit at ~2,107 ft (642 m) with preliminary BHP ≈ 953 psi; visible gas influx confirmed a strongly pressurized system.
  • Success Rate: All seven Jetstream appraisal wells drilled to date have intersected pressurized gas – 7‑for‑7 success.
  • Down‑hole Logging: Completed on 17 Mar 2026 by Extreme Wireline, including a full suite of logs (CMI). Logging truck now moving to Jetstream #6.
  • Jetstream #5 Operations: Drill rig mobilized to retrieve or bypass ~1,239 ft of drill string remaining in the well; after completion, rig will demobilize and the well will be prepared for logging and flow testing.
  • Flow & Pressure Build‑up Testing: Planned for late March–early April 2026 across all Jetstream wells; will provide quantitative data on gas rates and reservoir pressure behavior.
  • Seismic Data Processing: 2D active seismic acquired in Feb 2026 processed by Earth Signal (Calgary); dataset deemed high quality and now under interpretation by Chief Geologist Prof. Nick Schofield to refine structural models and guide future appraisal targeting.

Notable Quotes

“The successful completion of Jetstream #7 marks the end of an intensive and highly productive exploratory drilling campaign at Topaz… we are on the cusp of defining the scale and commercial potential of the Topaz resource.” – Thomas Abraham‑James, President & CEO, Pulsar Helium Inc.

Read the original news release →