NAM 0.250 +0.0% CRD 0.065 +8.3% OLA 12.90 −3.7% CG 22.70 −2.5% EQX 12.89 −4.0% FM 37.51 −2.3% MNRG 0.080 −11.1% KFR 1.31 +0.8% AUMN 0.275 +0.0% GLB 0.250 +0.0% BHS 0.045 −10.0% EGR 0.025 +0.0% RIO 2.59 −4.1% GEN 0.070 +0.0% MAI 4.39 −2.0% RYR 0.175 +0.0% NAM 0.250 +0.0% CRD 0.065 +8.3% OLA 12.90 −3.7% CG 22.70 −2.5% EQX 12.89 −4.0% FM 37.51 −2.3% MNRG 0.080 −11.1% KFR 1.31 +0.8% AUMN 0.275 +0.0% GLB 0.250 +0.0% BHS 0.045 −10.0% EGR 0.025 +0.0% RIO 2.59 −4.1% GEN 0.070 +0.0% MAI 4.39 −2.0% RYR 0.175 +0.0%
Production / Operations

Cdn Critical has $135K (U.S.) sales from BRM in August

CCMI · Price

Executive Summary

  • Canadian Critical Minerals reported $135,000 USD revenue from the sale of stockpiled copper‑gold‑silver mineralized material shipped from Bull River Mine in August 2025.
  • The sold material comprised 1,448 dry metric tonnes grading 1.39% Cu, 0.27 g/t Au and 12.2 g/t Ag.
  • Proceeds will fund continuing care & maintenance at the mine and engineering studies for the final permit application to restart milling and underground operations.

Key Details

  • Revenue: Approx. US$135,000 received on a provisional basis for August 2025 shipments.
  • Volume Shipped: 1,448 dry metric tonnes of unsorted mineralized fine material transported to New Afton.
  • Grades of Material Sold: 1.39 % Cu, 0.27 g/t Au, 12.2 g/t Ag.
  • Material Size: Fines < ‑5/8 in, too fine for segregation in the ore sorter.
  • Use of Proceeds: Offset costs associated with continuing care & maintenance (CCM) at Bull River Mine and fund engineering studies needed for final permit application to restart mill and underground operations.
  • Underground Status: Remains de‑watered and under CCM.
  • Ore Sorter Update: Decommissioned as of August month‑end; returned to owner in Idaho on 10 Sept 2025.