P2 Gold Gabbs Project Update

PGLD · Price
Executive Summary
- P2 Gold reports the commencement of RC drilling at the Sullivan Zone (12 of 24 holes completed) and outlines a subsequent 47‑hole, 10,000 m program at the Lucky Strike Zone.
- Diamond drilling is being mobilized for geotechnical and metallurgical sampling to support a forthcoming feasibility study; 17 holes (3,500 m total) are planned.
- The company has awarded multiple engineering and environmental contracts to advance the Gabbs Project feasibility study, with all field work expected to be completed by Q2 2026.
Key Details
- RC Drilling – Sullivan Zone: 12 reverse‑circulation holes finished; program totals 24 holes and ~4,900 m of drilling. Initial results anticipated before year‑end.
- Planned RC Drilling – Lucky Strike Zone: 47 infill/expansion holes targeting ~10,000 m once Sullivan work is complete.
- Diamond Drilling – Geotechnical & Metallurgical: Mobilizing a diamond rig for 17 holes (~3,500 m). Early holes will supply metallurgical samples for column leach tests and data for pit slope stability analyses at both zones.
- Feasibility‑Level Contracts Awarded:
- Barr Engineering – pit slope stability study (Sullivan & Lucky Strike).
- Kautz Environmental Consultants – cultural inventory of the mine site.
- Aqua Hydrogeologic Consulting – hydrogeologic modeling for open pits and process water rights.
- Western Biological – expanded biological survey.
- Kappas Cassiday – optimized heap‑leach and mill processing metallurgical studies.
- Welsh Hagen – geotechnical studies for leach pad and process facility foundations.
- Timeline: All drilling, contract work, and associated field studies are slated for completion in Q2 2026; an updated Mineral Resource estimate will follow, feeding into a revised mine plan and economic analysis.
- Qualified Person: Ken McNaughton, Chief Exploration Officer, has reviewed and approved the technical information per NI 43‑101.
Notable Quotes
(No direct quotes were provided in the release.)