LUN 33.59 −2.5% NTR 94.27 −1.8% LALI 0.055 −8.3% SCD 0.170 +0.0% HWY 0.370 +0.0% FCI 0.385 +1.3% GGAU 0.180 −5.3% KIRO 0.650 +1.6% LBNK 0.430 +0.0% BARU 0.040 +0.0% VCU 1.09 −4.4% NOBL 0.095 −5.0% SHL 0.355 +0.0% MTS 0.130 +0.0% FYL 0.090 +0.0% NUAG 5.55 +1.8% LUN 33.59 −2.5% NTR 94.27 −1.8% LALI 0.055 −8.3% SCD 0.170 +0.0% HWY 0.370 +0.0% FCI 0.385 +1.3% GGAU 0.180 −5.3% KIRO 0.650 +1.6% LBNK 0.430 +0.0% BARU 0.040 +0.0% VCU 1.09 −4.4% NOBL 0.095 −5.0% SHL 0.355 +0.0% MTS 0.130 +0.0% FYL 0.090 +0.0% NUAG 5.55 +1.8%
Production / Operations

Cardinal Provides an Update on the Operation of Its Thermal Business Unit and the De-Risking of Several Thermal Projects

CJ · Price

Executive Summary

  • Cardinal Energy provided a detailed update on its thermal oil development program, highlighting the successful ramp‑up of Reford 1 and outlining plans for two new SAGD projects – Reford 2 and Kelfield.
  • Reford 2 is projected to cost ~​$140 M (base) with an optional $40 M expansion, target design capacity 4,250 bbl/d (expandable to >6,500 bbl/d), and a two‑year payout at current strip prices.
  • Kelfield mirrors Reford 2’s design, targeting a minimum 4,000 bbl/d (expandable to >6,000 bbl/d) with similar capital requirements and timelines.

Key Details

  • Reford 1 Performance: Operating above its 6,000 bbl/d nameplate; aiming for 6,500 bbl/d in Q1 2026.
  • Reford 2 Project
  • 100% working interest acquired H2 2025.
  • Design capacity: 4,250 bbl/d (expandable to >6,500 bbl/d).
  • Estimated base capital cost: ≈ $140 M; additional $40 M for expansion to 6,500 bbl/d.
  • Construction timeline: ~18 months from start to first steam.
  • Projected operating life: ~20 years.
  • Expected payout: ~2 years at current strip oil prices.
  • Regulatory applications underway; design leverages proven Reford 1 facilities.

  • Kelfield Project

  • 100% working interest held.
  • Design capacity: minimum 4,000 bbl/d (expandable to >6,000 bbl/d).
  • Similar capital cost structure and construction timeline as Reford 2.
  • Projected operating life: ~20 years.
  • Regulatory applications underway; adopts Reford 1 facility design.

  • Additional Thermal Opportunities

  • Initiated technical program on two further prospects within existing land base.
  • Activities include re‑processing 3D seismic, re‑interpreting historic wells, drilling new stratigraphic wells, and updating reservoir models to refine resource estimates and deliverability.

  • Strategic Outlook

  • Ongoing discussions with Saskatchewan provincial ministries support long‑term thermal development across the land base.
  • Projects aim to contribute toward the province’s goal of 600,000 bbl/d total oil production.
  • Emphasis on capital efficiency, shared infrastructure, and responsible environmental stewardship.

Notable Quotes

No direct quotes were included in the release.

Read the original news release →