GOLD 4424.90 +0.6% SILVER 67.15 +1.6% COPPER 6.69 +0.5% OIL 96.08 −5.7% PALLADIUM 1319.50 +1.3% ARIC 0.760 −1.3% DCOP 0.095 +0.0% GLO 0.620 +3.3% CCM 0.770 +1.3% FAN 0.750 +2.7% FL 0.450 −1.6% BGF 0.030 +0.0% KLD 2.25 −0.4% SLVR 1.17 +1.7% LEM 0.250 +0.0% GENM 0.610 −3.2% SICO 9.80 +1.0% CTV 0.125 +0.0% CTM 0.140 +0.0% RSMX 0.110 −4.3% FT 0.145 +3.6% GOLD 4424.90 +0.6% SILVER 67.15 +1.6% COPPER 6.69 +0.5% OIL 96.08 −5.7% PALLADIUM 1319.50 +1.3% ARIC 0.760 −1.3% DCOP 0.095 +0.0% GLO 0.620 +3.3% CCM 0.770 +1.3% FAN 0.750 +2.7% FL 0.450 −1.6% BGF 0.030 +0.0% KLD 2.25 −0.4% SLVR 1.17 +1.7% LEM 0.250 +0.0% GENM 0.610 −3.2% SICO 9.80 +1.0% CTV 0.125 +0.0% CTM 0.140 +0.0% RSMX 0.110 −4.3% FT 0.145 +3.6%
Production / Operations

Ximen completes culvert design for Kenville

XIM · Price

Executive Summary

  • Ximen Mining Corp. is completing final pre-construction requirements to commence construction at its Kenville gold mine project in Nelson, British Columbia.
  • The company has received the engineered design for a critical culvert and runoff installation required across Fisherman Road, which must be completed before mine construction can begin.
  • Construction of the culvert is scheduled for early spring, with the company aiming to break ground on the new underground decline immediately following the completion of these pre-construction obligations.

Key Details

  • Culvert Design: A consultant engineer completed the design for a culvert and runoff installation to construct a culvert across Fisherman Road; this design has been provided to the B.C. Ministry of Transportation and Infrastructure.
  • Regulatory Requirement: The culvert serves as a drainage diversion upgrade that is a mandatory prerequisite for starting mine construction.
  • Construction Timeline: Construction of the culvert is planned for early spring.
  • Additional Engineering: A design for a water retention tank (to protect the drainage channel during flood events) is nearly complete.
  • Pending Reports: An engineering report regarding mine site building foundations and road stability is still required to be completed.
  • Project Status: The company aims to break ground for the new underground decline as soon as these preconstruction requirements are satisfied.
  • Technical Approval: Dr. Mathew Ball, PGeo, vice-president, exploration, approved the technical information as a qualified person under National Instrument 43-101.

Notable Quotes

  • "The culvert is a drainage diversion upgrade that is required to be in place before mine construction can be started."
  • "This is a major step forward toward starting the mine."
  • "The Kenville gold mine project continues moving forward."