Northwire Canada EditionSunday, July 12, 2026
Northwire
GLDN 0.055 +0.0% BRON 0.040 +0.0% BTO 5.43 −0.7% ESK 0.365 −2.7% AUMN 0.275 +0.0% GGX 0.040 +0.0% S 0.155 +29.2% NNX 0.035 +0.0% ABX 51.90 −0.6% TTS 2.40 −4.0% FCI 0.400 −9.1% GR 0.075 +0.0% AII 23.38 +12.4% TUNG 1.72 +1.8% LGO 1.01 −2.9% EMM 0.080 +0.0% GLDN 0.055 +0.0% BRON 0.040 +0.0% BTO 5.43 −0.7% ESK 0.365 −2.7% AUMN 0.275 +0.0% GGX 0.040 +0.0% S 0.155 +29.2% NNX 0.035 +0.0% ABX 51.90 −0.6% TTS 2.40 −4.0% FCI 0.400 −9.1% GR 0.075 +0.0% AII 23.38 +12.4% TUNG 1.72 +1.8% LGO 1.01 −2.9% EMM 0.080 +0.0%
Production / Operations

Westshore lowers 2025 throughput estimate over fire

WTE · Price

Executive Summary

  • Westshore Terminals experienced a fire on the shiploader servicing Berth 1 on August 16, 2025, resulting in an estimated 10-week outage for repairs to mechanical and electrical systems.
  • The company has revised its 2025 throughput guidance downward to 24.0–24.5 million tonnes, a reduction from the previous estimate of 26.0 million tonnes, due to the Berth 1 outage.
  • Operations at Berth 2 continue normally, and the company is working with customers and railways to mitigate the impact of the disruption.

Key Details

  • Incident Details: A fire occurred on the shiploader servicing Berth 1 on August 16, 2025. Fire crews extinguished the fire safely with no injuries reported.
  • Outage Duration: Berth 1 is estimated to be out of commission for approximately 10 weeks to repair mechanical and electrical systems, assuming no significant structural damage.
  • Inspection Status: A detailed inspection is pending to confirm the duration of the outage and the time required to source replacement parts/materials.
  • Operational Continuity: Operations at Berth 2 continue in the ordinary course. Westshore is collaborating with customers and railways to reduce the impact of the Berth 1 outage.
  • Guidance Revision: 2025 throughput volumes are now anticipated to be approximately 24.0 million to 24.5 million tonnes.
  • Previous Guidance: The prior estimate for 2025 throughput was approximately 26.0 million tonnes.

Notable Quotes

  • "At this time, based on preliminary limited inspection and assuming there is no significant structural damage, the company estimates berth 1 will be out of commission for approximately 10 weeks to perform the necessary repairs to the mechanical and electrical systems."
Read the original news release →

More from Westshore Terminals Investment Corp