NAM 0.250 +0.0% CRD 0.065 +8.3% OLA 12.90 −3.7% CG 22.70 −2.5% EQX 12.89 −4.0% FM 37.51 −2.3% MNRG 0.080 −11.1% KFR 1.31 +0.8% AUMN 0.275 +0.0% GLB 0.250 +0.0% BHS 0.045 −10.0% EGR 0.025 +0.0% RIO 2.59 −4.1% GEN 0.070 +0.0% MAI 4.39 −2.0% RYR 0.175 +0.0% NAM 0.250 +0.0% CRD 0.065 +8.3% OLA 12.90 −3.7% CG 22.70 −2.5% EQX 12.89 −4.0% FM 37.51 −2.3% MNRG 0.080 −11.1% KFR 1.31 +0.8% AUMN 0.275 +0.0% GLB 0.250 +0.0% BHS 0.045 −10.0% EGR 0.025 +0.0% RIO 2.59 −4.1% GEN 0.070 +0.0% MAI 4.39 −2.0% RYR 0.175 +0.0%
Production / Operations

American Tungsten expands Ima phase 1 drill program

TUNG · Price

Executive Summary

  • American Tungsten Corp. announced significant progress on the rehabilitation and development of its Ima mine project in Idaho, specifically regarding Phase 1 drilling preparations.
  • The company expanded the Phase 1 drilling program scope to include approximately 10,000 feet of drilling across three stations on the D level and two stations on the Zero level to test geological continuity and additional vein systems.
  • CEO Ali Haji will host a live investor webinar on November 18 to discuss operational milestones, while the company also engaged Gold Standard Media LLC for investor relations marketing services.

Key Details

  • Drilling Program Expansion: Phase 1 drilling scope expanded to ~10,000 feet across 5 stations (3 on D level, 2 on Zero level).
  • Objective: Establish geological continuity of the polymetallic tungsten quartz vein system up-dip of the D level and test additional vein systems from the Zero level (previously intersected in mid-2000s Gentor drill holes).
  • D-Level Progress:
    • Access crosscut excavation is ~54% complete (~100 feet done, ~86 feet remaining).
    • First diamond drill station expected to be reached by the end of the week following the release.
    • Drill rig and power packs are on site, awaiting mobilization underground.
    • Development of access drifts continues toward the second and third stations.
    • Work is being double-shifted by the contractor to expedite the timeline.
  • Zero-Level Progress:
    • Rehabilitation continues; remaining visible debris area estimated to be cleared by the end of the following week.
    • Clearance will allow access to previously rehabilitated areas and new drifts around unstable areas from 1970s operations.
    • Company will assess additional rehabilitation needs to support drilling from the Zero level.
    • Additional staff secured to perform work in parallel with D-level progress.
  • Future Planning: Initial planning for Phase 2 of the diamond drill program has begun, extending the scope into Q1 2026.
  • Investor Webinar: CEO Ali Haji to host a live webinar on Tuesday, Nov. 18 at 10 a.m. ET/7 a.m. PT to discuss corporate updates, milestones, and answer investor questions.
  • Marketing Agreement: Entered into a marketing agreement with Gold Standard Media LLC (GSM) for landing pages, digital marketing, e-mail marketing, and influencer services.
  • Consideration: GSM to be paid a cash fee of $48,000 (U.S.).

Notable Quotes

  • No direct quotes from the CEO or management were included in the text provided.