Northwire Canada EditionTuesday, July 14, 2026
Northwire
FAIR 0.055 +22.2% SVRS 0.430 +0.0% RES 0.035 +0.0% CYG 0.120 +0.0% MGG 0.320 −3.0% BUFF 0.770 +2.7% TKO 10.83 +8.7% MINK 0.115 +9.5% LCE 0.250 +0.0% AEF 0.160 +0.0% BEM 0.095 +5.6% APMI 0.120 +0.0% LIO 0.135 +3.9% KC 0.260 −3.7% NOVA 0.170 +3.0% FAIR 0.055 +22.2% SVRS 0.430 +0.0% RES 0.035 +0.0% CYG 0.120 +0.0% MGG 0.320 −3.0% BUFF 0.770 +2.7% TKO 10.83 +8.7% MINK 0.115 +9.5% LCE 0.250 +0.0% AEF 0.160 +0.0% BEM 0.095 +5.6% APMI 0.120 +0.0% LIO 0.135 +3.9% KC 0.260 −3.7% NOVA 0.170 +3.0%
Production / Operations

Taseko Mines harvests first copper cathodes at Florence

TKO · Price

Executive Summary

  • Taseko Mines Ltd. has harvested its first copper cathodes at the Florence Copper operation in Arizona, marking the first new copper production from a greenfield facility in the United States since 2008.
  • The production utilizes ISCR (in situ copper recovery), a unique low-cost method with environmental advantages over conventional mining.
  • Upon reaching nameplate capacity, Taseko will become the third-largest copper cathode producer in America, with an expected minimum production of 1.5 billion pounds of copper over the next 22 years.

Key Details

  • Milestone: First copper cathodes harvested from the recently completed commercial production facility at Florence Copper.
  • Production Capacity: Nameplate capacity is 85 million pounds of LME Grade A copper metal per year.
  • Long-Term Outlook: The operation is expected to produce a minimum of 1.5 billion pounds of copper over the next 22 years.
  • Market Position: Once at nameplate capacity, Taseko will become the third-largest copper cathode producer in the United States.
  • Technology: The site is the first greenfield site globally to employ ISCR (in situ copper recovery), described as a low-cost method with compelling environmental advantages.
  • Strategic Context: Production supports U.S. manufacturing and supply chain security for sectors including automotive, semiconductor, defense/aerospace, and AI data centers. All produced copper will remain in the United States.
  • Project Status: Construction was completed on time and on budget following extensive test work and permitting.

Notable Quotes

  • "The production of first copper in Arizona represents a landmark achievement for the Florence copper team and a major milestone for Taseko as we continue our journey to become a leading North American copper producer." — Stuart McDonald, President and CEO
  • "Producing LME Grade A copper cathode for America's manufacturing sector... will meaningfully strengthen U.S. manufacturing and supply chain security." — Stuart McDonald
  • "The journey to first production at Florence copper... is a testament to the resourcefulness, purpose and commitment of the entire Taseko team." — Stuart McDonald
Read the original news release →