Northwire Canada EditionSaturday, August 1, 2026
Northwire
S 0.140 +0.0% BNKR 4.40 −2.2% QRO 0.045 +0.0% VCT 0.075 +36.4% PPP 1.15 +0.9% LMG 0.390 +0.0% GRDM 0.140 +0.0% ABRA 13.58 −4.1% WHY 0.295 +1.7% HHH 3.94 −0.2% COS 0.060 +0.0% NOB 0.065 −23.5% MEK 0.055 +0.0% TGOL 0.105 −4.5% FCI 0.400 −7.0% SGQ 0.350 +0.0% S 0.140 +0.0% BNKR 4.40 −2.2% QRO 0.045 +0.0% VCT 0.075 +36.4% PPP 1.15 +0.9% LMG 0.390 +0.0% GRDM 0.140 +0.0% ABRA 13.58 −4.1% WHY 0.295 +1.7% HHH 3.94 −0.2% COS 0.060 +0.0% NOB 0.065 −23.5% MEK 0.055 +0.0% TGOL 0.105 −4.5% FCI 0.400 −7.0% SGQ 0.350 +0.0%
Production / Operations

Sixty North spends $6.2M since 2017 on Mon development

SXTY · Price

Executive Summary

  • Sixty North Gold Mining Ltd. provided a detailed operational update regarding the development of its Mon gold mine, outlining historical expenditures, current development progress, and future production plans.
  • The company has invested $6.2 million since 2017, with $3.6 million allocated to exploration and development, including equipment and labor.
  • Future plans include accessing the A-zone quartz veins, installing a 100-tonne-per-day mill in spring 2026, and scaling up labor for full production operations.

Key Details

  • Historical Expenditures: Total investment of $6.2 million since 2017, comprising:
    • $2.6 million in acquisition costs.
    • $3.6 million in exploration and development costs, broken down as:
      • $427,540 in recoverable reclamation bonds.
      • $900,000 on mining and operations equipment.
      • $2.2 million on development labour and consumables.
  • Development Progress:
    • 226 metres of development completed, including portal repair, ramp slashing/advancing, crosscut drives, and service installation.
    • Successfully accessed the A-zone quartz veins below two historic stopes.
    • Historic stopes extracted 112 metres of strike length; each 15m elevation yielded 15,000 tonnes of ore at a reconciled grade of 30 g/t gold (1,000 oz gold per vertical metre).
  • Operational Costs (2024):
    • Direct operating costs: $10,000 per day or $4,800 per metre advanced.
    • Cost per tonne of rock extracted in development: $143.
    • Staffing basis: Two miners (single shift), mine manager, geologist, mechanic, and support staff.
  • Future Production Plans (2026):
    • Plan to subdrift north and south on both east and west limbs of the A-zone for a total of 137m of the quartz vein (16m and 18m below existing stopes).
    • Extraction method: Mechanized resue method in four stopes to minimize dilution and maximize extraction.
    • Target recovery: Approximately 20,000 tonnes of A-zone vein.
    • Cost expectation: Initially similar to previous costs, potentially reducing as more vein characteristics are revealed.
  • Mill and Capital Requirements:
    • Sourced a 100-tonne-per-day mill.
    • Acquisition, transportation, and installation planned for spring 2026.
    • Capital costs quoted at approximately $1 million.
    • Additional $344,564 in environmental bonding required prior to mill installation and operation.
  • Full Production Staffing and Costs:
    • Additional crew needed: Second two-man mining crew, two mill operators, two support crew, and an additional mechanic.
    • Labor cost increase: 50% increase to approximately $15,000 per day.
    • Consumables (fuel/explosives) increase: To nearly $5,000 per day.
  • Technical Reporting Status:
    • No National Instrument 43-101 technical report recommending a decision to proceed to production has been completed or is contemplated at this time.
    • Reference to previous 1990s production: 15,000 ounces of gold extracted from 15,000 tonnes of ore without a feasibility study or reserve report.
    • Warning issued regarding increased uncertainty and economic/technical risks associated with production decisions lacking a feasibility study.

Notable Quotes

  • "Dr. D.R. Webb, PhD, PGeol, PEng, president and chief executive officer of the company, is the qualified person for this release, and has reviewed and approved of its technical content."
Read the original news release →

More from Sixty North Gold Mining Ltd