Production / Operations
Sixty North spends $6.2M since 2017 on Mon development

SXTY · Price
Executive Summary
- Sixty North Gold Mining Ltd. provided a detailed operational update regarding the development of its Mon gold mine, outlining historical expenditures, current development progress, and future production plans.
- The company has invested $6.2 million since 2017, with $3.6 million allocated to exploration and development, including equipment and labor.
- Future plans include accessing the A-zone quartz veins, installing a 100-tonne-per-day mill in spring 2026, and scaling up labor for full production operations.
Key Details
- Historical Expenditures: Total investment of $6.2 million since 2017, comprising:
- $2.6 million in acquisition costs.
- $3.6 million in exploration and development costs, broken down as:
- $427,540 in recoverable reclamation bonds.
- $900,000 on mining and operations equipment.
- $2.2 million on development labour and consumables.
- Development Progress:
- 226 metres of development completed, including portal repair, ramp slashing/advancing, crosscut drives, and service installation.
- Successfully accessed the A-zone quartz veins below two historic stopes.
- Historic stopes extracted 112 metres of strike length; each 15m elevation yielded 15,000 tonnes of ore at a reconciled grade of 30 g/t gold (1,000 oz gold per vertical metre).
- Operational Costs (2024):
- Direct operating costs: $10,000 per day or $4,800 per metre advanced.
- Cost per tonne of rock extracted in development: $143.
- Staffing basis: Two miners (single shift), mine manager, geologist, mechanic, and support staff.
- Future Production Plans (2026):
- Plan to subdrift north and south on both east and west limbs of the A-zone for a total of 137m of the quartz vein (16m and 18m below existing stopes).
- Extraction method: Mechanized resue method in four stopes to minimize dilution and maximize extraction.
- Target recovery: Approximately 20,000 tonnes of A-zone vein.
- Cost expectation: Initially similar to previous costs, potentially reducing as more vein characteristics are revealed.
- Mill and Capital Requirements:
- Sourced a 100-tonne-per-day mill.
- Acquisition, transportation, and installation planned for spring 2026.
- Capital costs quoted at approximately $1 million.
- Additional $344,564 in environmental bonding required prior to mill installation and operation.
- Full Production Staffing and Costs:
- Additional crew needed: Second two-man mining crew, two mill operators, two support crew, and an additional mechanic.
- Labor cost increase: 50% increase to approximately $15,000 per day.
- Consumables (fuel/explosives) increase: To nearly $5,000 per day.
- Technical Reporting Status:
- No National Instrument 43-101 technical report recommending a decision to proceed to production has been completed or is contemplated at this time.
- Reference to previous 1990s production: 15,000 ounces of gold extracted from 15,000 tonnes of ore without a feasibility study or reserve report.
- Warning issued regarding increased uncertainty and economic/technical risks associated with production decisions lacking a feasibility study.
Notable Quotes
- "Dr. D.R. Webb, PhD, PGeol, PEng, president and chief executive officer of the company, is the qualified person for this release, and has reviewed and approved of its technical content."
More from Sixty North Gold Mining Ltd
Jun 19, 2026 · 09:37