B 0.150 +0.0% IFOS 2.28 −2.6% IMM 0.060 +0.0% ROCK 3.38 −1.7% NVX 0.250 −7.4% HAR 0.050 +0.0% YGT 0.175 +0.0% GEN 0.070 −nan% CRB 0.040 +14.3% MSA 7.07 +2.2% AEM 204.81 +0.7% OPW 0.105 +5.0% GRL 0.275 −1.8% AIS 0.150 +0.0% CUU 0.580 −1.7% SOMA 0.720 +5.9% B 0.150 +0.0% IFOS 2.28 −2.6% IMM 0.060 +0.0% ROCK 3.38 −1.7% NVX 0.250 −7.4% HAR 0.050 +0.0% YGT 0.175 +0.0% GEN 0.070 −nan% CRB 0.040 +14.3% MSA 7.07 +2.2% AEM 204.81 +0.7% OPW 0.105 +5.0% GRL 0.275 −1.8% AIS 0.150 +0.0% CUU 0.580 −1.7% SOMA 0.720 +5.9%
Production / Operations

Sixty North begins construction of winter road to Mon

SXTY · Price

Executive Summary

  • Sixty North Gold Mining Ltd. provided a progress update on its Mon gold mine in Yellowknife, NWT, confirming that construction of the winter road has commenced to facilitate the start of gold production this year.
  • The company plans to haul 19 truckloads of supplies, including a 100-tonne-per-day (tpd) mill, to the site in February and March.
  • Mill assembly is scheduled for late April, with initial commissioning targeted for June and July, operating 24/7 to treat material from the second level of the A zone vein.

Key Details

  • Winter Road Construction: Construction of the southern half of the winter road has started from Highway 4, 20 km east of Yellowknife, extending northward across Prosperous Lake for approximately 15 km.
  • Logistics Management: The remaining balance of the road to the Mon gold mine site (approximately 30 km farther north) will be installed and managed by Matrix, commencing next month.
  • Supply Haul: A total of 19 truckloads of supplies, including the 100-tpd mill, will be hauled to the site in February and March.
  • Mill Operations:
    • Assembly of the 100 tpd mill is planned for late April.
    • Initial commissioning is scheduled for June and July.
    • The mill will operate 24/7.
    • It will treat material extracted from the second level of the A zone vein below the historic stopes.
  • Underground Development Plans:
    • The DD zone will be evaluated for potential stope development.
    • The company plans to extend the main ramp to the third level.
  • Historical Context: Mining in the 1990s extracted 15,000 tonnes of ore to depths of only 15 metres below surface, recovering an estimated 15,000 ounces of gold.
  • Recent Exploration: Underground development has intersected the productive A zone 17 metres below the historic stopes and a newly identified zone, the DD zone, in the main ramp.

Notable Quotes

  • "We are very pleased with progress this winter. The installation of the winter road is an important part of our operations. Cold weather with limited snow is creating thick ice, enabling faster and stronger roads to be constructed. Our plans are to get the mill operating as expeditiously as possible." — Dave Webb, President and CEO