ZAC 0.060 +0.0% ELE 21.18 −1.7% GHRT 0.750 +0.0% AEM 203.13 +0.1% JTWO 0.135 +0.0% EDR 10.63 −2.8% VMXX 0.750 +5.6% K 32.71 −1.5% AGI 40.13 −1.4% VGZ 2.40 +0.8% CAN 0.055 +0.0% NVO 0.055 +0.0% ARIS 19.57 −4.2% IVN 10.59 −0.8% MCI 0.165 +0.0% MTS 0.130 +0.0% ZAC 0.060 +0.0% ELE 21.18 −1.7% GHRT 0.750 +0.0% AEM 203.13 +0.1% JTWO 0.135 +0.0% EDR 10.63 −2.8% VMXX 0.750 +5.6% K 32.71 −1.5% AGI 40.13 −1.4% VGZ 2.40 +0.8% CAN 0.055 +0.0% NVO 0.055 +0.0% ARIS 19.57 −4.2% IVN 10.59 −0.8% MCI 0.165 +0.0% MTS 0.130 +0.0%
Technical Study

Orla files NI 43-101 tech report for South Railroad

OLA · Price

Executive Summary

  • Orla Mining Ltd. has filed an updated independent technical report for its South Railroad gold project in Nevada, prepared in accordance with National Instrument 43-101.
  • The report includes a construction-ready feasibility study featuring a two-stage crushing circuit for improved recoveries and a comprehensive execution plan for the project's transition into development.
  • The company is currently in the execution phase, focusing on detailed engineering and long-lead procurement, with full construction expected to commence in mid-2026 pending final permits.

Key Details

  • Report Filing: Updated independent technical report for the South Railroad gold project filed under National Instrument 43-101.
  • Project Location: Nevada, United States; part of the South Carlin complex land package on the Carlin trend.
  • Feasibility Study Enhancements:
    • Includes a two-stage crushing circuit designed for improved gold recoveries.
    • Features expanded metallurgical testing.
    • Contains a comprehensive execution plan to support the transition from exploration/feasibility to development.
  • Current Operational Status: Transitioning to the execution phase; focus areas include detailed engineering, construction readiness, and long-lead procurement.
  • Construction Timeline: Full construction expected to commence in mid-2026, pending receipt of final project permits.
  • Financing Strategy: Development is expected to be financed through operating cash flow and cash on hand.
  • Availability: The technical report is available on SEDAR+, EDGAR, and Orla Mining’s website.
  • Qualified Person: J. Andrew Cormier, PEng, Chief Operating Officer, reviewed and approved the scientific and technical information.

Notable Quotes

  • "The South Railroad technical report now includes a construction-ready feasibility study backed by advanced engineering and expanded metallurgical testing."