Gold 4,029.40 −2.1% Silver 51.33 −2.6% Copper 6.23 −1.8% Oil 86.60 −0.3% Palladium 1,018.50 −0.3% SMP 0.050 +0.0% FUSE 0.020 −20.0% COPR 0.380 +1.3% WSK 0.170 +0.0% GAL 0.375 −1.3% VCG 1.05 +2.9% LVX 0.270 −20.6% RAMP 0.250 −7.4% QTWO 1.71 +6.2% SUM 1.28 −3.0% SGML 7.53 −9.8% BOGO 0.750 −5.1% SGC 0.095 +0.0% MANU 0.172 +15.0% GMA 0.200 +0.0% ONAU 0.460 −3.2% Gold 4,029.40 −2.1% Silver 51.33 −2.6% Copper 6.23 −1.8% Oil 86.60 −0.3% Palladium 1,018.50 −0.3% SMP 0.050 +0.0% FUSE 0.020 −20.0% COPR 0.380 +1.3% WSK 0.170 +0.0% GAL 0.375 −1.3% VCG 1.05 +2.9% LVX 0.270 −20.6% RAMP 0.250 −7.4% QTWO 1.71 +6.2% SUM 1.28 −3.0% SGML 7.53 −9.8% BOGO 0.750 −5.1% SGC 0.095 +0.0% MANU 0.172 +15.0% GMA 0.200 +0.0% ONAU 0.460 −3.2%
Technical Study

Orla files NI 43-101 tech report for South Railroad

OLA · Price

Executive Summary

  • Orla Mining Ltd. has filed an updated independent technical report for its South Railroad gold project in Nevada, prepared in accordance with National Instrument 43-101.
  • The report includes a construction-ready feasibility study featuring a two-stage crushing circuit for improved recoveries and a comprehensive execution plan for the project's transition into development.
  • The company is currently in the execution phase, focusing on detailed engineering and long-lead procurement, with full construction expected to commence in mid-2026 pending final permits.

Key Details

  • Report Filing: Updated independent technical report for the South Railroad gold project filed under National Instrument 43-101.
  • Project Location: Nevada, United States; part of the South Carlin complex land package on the Carlin trend.
  • Feasibility Study Enhancements:
    • Includes a two-stage crushing circuit designed for improved gold recoveries.
    • Features expanded metallurgical testing.
    • Contains a comprehensive execution plan to support the transition from exploration/feasibility to development.
  • Current Operational Status: Transitioning to the execution phase; focus areas include detailed engineering, construction readiness, and long-lead procurement.
  • Construction Timeline: Full construction expected to commence in mid-2026, pending receipt of final project permits.
  • Financing Strategy: Development is expected to be financed through operating cash flow and cash on hand.
  • Availability: The technical report is available on SEDAR+, EDGAR, and Orla Mining’s website.
  • Qualified Person: J. Andrew Cormier, PEng, Chief Operating Officer, reviewed and approved the scientific and technical information.

Notable Quotes

  • "The South Railroad technical report now includes a construction-ready feasibility study backed by advanced engineering and expanded metallurgical testing."