Lithium Ionic working toward construction at Bandeira

LTH · Price
Executive Summary
- Lithium Ionic Corp. reports that engineering at its 100%-owned Bandeira lithium project in Brazil has reached 48% completion, with basic plant and primary civil engineering finished.
- The company has received multiple term sheets for offtake and debt financing, advancing toward binding agreements, while strengthening its executive team with new hires in ESG, finance, and community relations.
- Lithium market conditions have improved significantly since the September 2025 feasibility study, with spodumene concentrate prices rising over 125% to over $1,800/tonne, enhancing the project's economic outlook.
Key Details
- Engineering Progress:
- Total project engineering is 48% complete.
- Basic engineering is complete for major design packages, including plant engineering and primary civil engineering (roads, plant areas, buildings).
- Detailed engineering for raw water and drainage is in the final stage.
- Underground mine development planning is advancing; NCL Ingenieria y Construccion SpA is mobilized to complete the detailed underground mine plan and schedule, targeted for April 2026.
- Procurement and Tendering:
- 23% of infrastructure procurement packages have been tendered to date.
- Tendering activities are underway for earthworks, drainage, mine access development, and site infrastructure.
- Mine underground contractor and mine fleet tendering are launching.
- Commercial and Financing:
- The company has received multiple offtake and debt financing term sheets from parties in North America, Europe, China, and Japan.
- Lead parties have completed due diligence, including concentrate testing and site visits.
- The company is advancing toward binding offtake agreements to support project debt financing.
- Management and Technical Support:
- Added a Director of Environmental, Social and Governance (ESG) and permitting.
- Added an Aracuai-based community relations manager.
- Recruited a Director of Finance for cost control and financing readiness.
- Engaged Jon Treen (Fuse Advisors) as an independent underground mining specialist.
- SRK Consulting is auditing geotechnical models for underground mine design.
- RTEK International DMCC has expanded technical support in electrical and instrumentation disciplines.
- Permitting and ESG:
- Environmental licensing application submitted on Jan. 26, 2024.
- FEAM issued a favourable technical opinion in Feb. 2025 recommending approval.
- Water rights for the Piaui and Jequitinhonha rivers have been secured.
- Explosives purchasing authorization obtained from the Brazilian Army.
- Design elements include dry-stacked tailings, maximized water recovery, and low-carbon hydroelectric power.
- Market Conditions:
- Spodumene concentrate (6% Li2O, delivered to Asia) price increased by >125% from ~$800/tonne (Sept 2025) to >$1,800/tonne (Feb 2026).
- Current pricing outperforms the near-term price scenario used in the project economic plan.
Notable Quotes
- "Bandeira is now firmly in the execution phase. With a technically robust and optimized feasibility study in hand, our focus has shifted to disciplined delivery -- advancing engineering, securing the right commercial partnerships and preparing the project for construction. Importantly, this progress is unfolding in a materially stronger lithium market than when our feasibility study was completed, which reinforces our confidence in the project's long-term value. Our objective is clear: to bring Brazil's next high-quality, low-cost lithium operation into production with the right foundations in place." — Blake Hylands, CEO