S 0.140 +0.0% BNKR 4.40 −2.2% QRO 0.045 +0.0% VCT 0.075 +36.4% PPP 1.15 +0.9% LMG 0.390 +0.0% GRDM 0.140 +0.0% ABRA 13.58 −4.1% WHY 0.295 +1.7% HHH 3.94 −0.2% COS 0.060 +0.0% NOB 0.065 −23.5% MEK 0.055 +0.0% TGOL 0.105 −4.5% FCI 0.400 −7.0% SGQ 0.350 +0.0% S 0.140 +0.0% BNKR 4.40 −2.2% QRO 0.045 +0.0% VCT 0.075 +36.4% PPP 1.15 +0.9% LMG 0.390 +0.0% GRDM 0.140 +0.0% ABRA 13.58 −4.1% WHY 0.295 +1.7% HHH 3.94 −0.2% COS 0.060 +0.0% NOB 0.065 −23.5% MEK 0.055 +0.0% TGOL 0.105 −4.5% FCI 0.400 −7.0% SGQ 0.350 +0.0%
Production / Operations

Denarius Metals begins work for Aguablanca restart

DMET · Price

Executive Summary

  • Denarius Metals Corp. has commenced activities to restart mining operations at its Aguablanca nickel-copper project in Spain, which is recognized by the EU as a strategic project under the Critical Raw Materials Act.
  • The company has engaged Metso to lead the refurbishment of the 5,000-tonnes-per-day processing plant, with Metso providing financing for phase 2 (reconditioning) and phase 3 (commissioning).
  • The company targets a return to production by mid-2026, with an expected output of approximately 70,000 tonnes per year of nickel-copper concentrates.

Key Details

  • Restart Timeline: Underground mine back in production expected by mid-2026.
  • Production Targets: Processing material at a rate of over 800,000 tonnes per year; producing an average of approximately 70,000 tonnes per year of nickel-copper concentrates.
  • Processing Plant Refurbishment:
    • Metso engaged to lead work on the 5,000-tonnes-per-day processing plant.
    • Phase 1: Detailed assessment of existing facility condition commencing in September (signed with Metso Spain SA).
    • Phase 2: Reconditioning services financed by Metso.
    • Phase 3: Commissioning carried out by a Portuguese industrial maintenance company under Metso supervision.
    • Maintenance and commissioning activities expected to last no longer than eight months.
  • Dewatering Program:
    • Pilot activities commenced in July with a 10-nozzle forced evaporation system for the tailings dam.
    • Two additional high-capacity evaporators to be installed in August.
    • Dewatering of the existing open pit to commence in October to gain access to underground workings.
    • Design and engineering completed; installation scheduled for September.
    • Dewatering activities expected to last no longer than six months.
  • Underground Infrastructure:
    • Negotiations underway with Endesa for underground electrical connections.
    • Underground assessment of ventilation, ramp access, and power to commence after dewatering.
    • Construction of a new escapeway system to commence after dewatering of the main ramp is completed.
  • Exploration Plans: Brownfield drilling program designed to commence in 2026, aimed at extending mine life, expanding reserves in known orebodies, and expanding the resource footprint of satellite mineralization.
  • Ownership Structure: Aguablanca project is 100% owned by Rio Narcea Recursos SA (RNR). Denarius Metals owns 21% of RNR via its subsidiary Alto Minerals SLU and acts as the operator.
  • Financing: In addition to Metso financing, Denarius is securing additional project financing directly through RNR for capital expenditures associated with start-up activities.

Notable Quotes

  • "In our capacity as operator, we have initiated activities to restart mining operations at the Aguablanca project, the only nickel mine in Spain that has also been recognized by the EU [European Union] as a strategic project under the Critical Raw Materials Act." — Serafino Iacono, Executive Chairman
Read the original news release →