Northwire Canada EditionThursday, October 15, 2026
Northwire
⌕
GOLD 4179.00 +1.7% SILVER 57.27 +2.5% COPPER 6.55 −1.6% OIL 97.90 +3.0% PALLADIUM 1133.75 +3.4% STND 0.060 −7.7% B 0.580 +1.8% HBM 34.05 −1.3% NTR 98.76 −0.7% SGZ 0.035 +0.0% MKA 0.670 +0.0% LXM 0.195 −9.3% CLCH 1.09 −0.9% NSU 0.170 +9.7% WM 0.085 +0.0% YGT 0.180 +5.9% EVI 0.500 +0.0% ADZ 0.125 +0.0% MINK 0.075 +0.0% DNO 0.300 +0.0% RRRL 0.150 +0.0% GOLD 4179.00 +1.7% SILVER 57.27 +2.5% COPPER 6.55 −1.6% OIL 97.90 +3.0% PALLADIUM 1133.75 +3.4% STND 0.060 −7.7% B 0.580 +1.8% HBM 34.05 −1.3% NTR 98.76 −0.7% SGZ 0.035 +0.0% MKA 0.670 +0.0% LXM 0.195 −9.3% CLCH 1.09 −0.9% NSU 0.170 +9.7% WM 0.085 +0.0% YGT 0.180 +5.9% EVI 0.500 +0.0% ADZ 0.125 +0.0% MINK 0.075 +0.0% DNO 0.300 +0.0% RRRL 0.150 +0.0%
Production / Operations

CARIBBEAN UTILITIES COMPANY, LTD WELCOMES REGULATORY APPROVAL OF THE CERTIFICATE OF NEED

CUP · Price

Executive Summary

  • Caribbean Utilities Company, Ltd. (CUC) received regulatory approval from the Utility Regulation and Competition Office (URCO) for its revised Certificate of Need (CON).
  • The approved CON establishes the requirement for 94 megawatts (MW) of additional generation capacity to support Grand Cayman's growing electricity demand.
  • The capacity is structured into three distinct blocks to allow for competitive procurement and the participation of alternate generation technologies.

Key Details

  • Regulatory Approval: URCO approved CUC's revised CON, which was originally submitted on February 10, 2026.
  • Capacity Requirements: The CON identifies future electricity needs and mandates the development of 94 MW of additional generation capacity.
  • Procurement Structure: The required capacity is divided into three distinct capacity blocks, facilitating a competitive procurement process for new generation resources.
  • Investment Context: CUC invests up to US$100 million annually in system reliability and resilience. Since 2020, these investments have contributed to a 50% reduction in outage time.
  • Demand Metrics: Electricity demand on Grand Cayman is increasing, with a record peak load of 129.5 MW recorded on July 31, 2025.
  • Regulatory Obligation: Under its Transmission and Distribution licence, CUC is required to submit a CON to outline projected demand, after which the Regulator launches a competitive procurement process.

Notable Quotes

  • "Energy is an essential service; the approval of the CON is an important step towards meeting Grand Cayman's growing electricity demand and providing a safe and reliable supply of electricity to the households and businesses we serve in the coming years." — Mr. Richard Hew, CUC President and CEO
Read the original news release →

More from