Northwire Canada EditionSunday, July 12, 2026
Northwire
GLDN 0.055 +0.0% BRON 0.040 +0.0% BTO 5.43 −0.7% ESK 0.365 −2.7% AUMN 0.275 +0.0% GGX 0.040 +0.0% S 0.155 +29.2% NNX 0.035 +0.0% ABX 51.90 −0.6% TTS 2.40 −4.0% FCI 0.400 −9.1% GR 0.075 +0.0% AII 23.38 +12.4% TUNG 1.72 +1.8% LGO 1.01 −2.9% EMM 0.080 +0.0% GLDN 0.055 +0.0% BRON 0.040 +0.0% BTO 5.43 −0.7% ESK 0.365 −2.7% AUMN 0.275 +0.0% GGX 0.040 +0.0% S 0.155 +29.2% NNX 0.035 +0.0% ABX 51.90 −0.6% TTS 2.40 −4.0% FCI 0.400 −9.1% GR 0.075 +0.0% AII 23.38 +12.4% TUNG 1.72 +1.8% LGO 1.01 −2.9% EMM 0.080 +0.0%
Production / Operations

CARIBBEAN UTILITIES COMPANY, LTD WELCOMES REGULATORY APPROVAL OF THE CERTIFICATE OF NEED

CUP · Price

Executive Summary

  • Caribbean Utilities Company, Ltd. (CUC) received regulatory approval from the Utility Regulation and Competition Office (URCO) for its revised Certificate of Need (CON).
  • The approved CON establishes the requirement for 94 megawatts (MW) of additional generation capacity to support Grand Cayman's growing electricity demand.
  • The capacity is structured into three distinct blocks to allow for competitive procurement and the participation of alternate generation technologies.

Key Details

  • Regulatory Approval: URCO approved CUC's revised CON, which was originally submitted on February 10, 2026.
  • Capacity Requirements: The CON identifies future electricity needs and mandates the development of 94 MW of additional generation capacity.
  • Procurement Structure: The required capacity is divided into three distinct capacity blocks, facilitating a competitive procurement process for new generation resources.
  • Investment Context: CUC invests up to US$100 million annually in system reliability and resilience. Since 2020, these investments have contributed to a 50% reduction in outage time.
  • Demand Metrics: Electricity demand on Grand Cayman is increasing, with a record peak load of 129.5 MW recorded on July 31, 2025.
  • Regulatory Obligation: Under its Transmission and Distribution licence, CUC is required to submit a CON to outline projected demand, after which the Regulator launches a competitive procurement process.

Notable Quotes

  • "Energy is an essential service; the approval of the CON is an important step towards meeting Grand Cayman's growing electricity demand and providing a safe and reliable supply of electricity to the households and businesses we serve in the coming years." — Mr. Richard Hew, CUC President and CEO
Read the original news release →

More from