Production / Operations
CARIBBEAN UTILITIES COMPANY, LTD WELCOMES REGULATORY APPROVAL OF THE CERTIFICATE OF NEED

CUP · Price
Executive Summary
- Caribbean Utilities Company, Ltd. (CUC) received regulatory approval from the Utility Regulation and Competition Office (URCO) for its revised Certificate of Need (CON).
- The approved CON establishes the requirement for 94 megawatts (MW) of additional generation capacity to support Grand Cayman's growing electricity demand.
- The capacity is structured into three distinct blocks to allow for competitive procurement and the participation of alternate generation technologies.
Key Details
- Regulatory Approval: URCO approved CUC's revised CON, which was originally submitted on February 10, 2026.
- Capacity Requirements: The CON identifies future electricity needs and mandates the development of 94 MW of additional generation capacity.
- Procurement Structure: The required capacity is divided into three distinct capacity blocks, facilitating a competitive procurement process for new generation resources.
- Investment Context: CUC invests up to US$100 million annually in system reliability and resilience. Since 2020, these investments have contributed to a 50% reduction in outage time.
- Demand Metrics: Electricity demand on Grand Cayman is increasing, with a record peak load of 129.5 MW recorded on July 31, 2025.
- Regulatory Obligation: Under its Transmission and Distribution licence, CUC is required to submit a CON to outline projected demand, after which the Regulator launches a competitive procurement process.
Notable Quotes
- "Energy is an essential service; the approval of the CON is an important step towards meeting Grand Cayman's growing electricity demand and providing a safe and reliable supply of electricity to the households and businesses we serve in the coming years." — Mr. Richard Hew, CUC President and CEO
More from
May 11, 2026 · 08:34