Production / Operations
Critical Infra's first Nexus20 units reach facility

CTTT · Price
Executive Summary
- Critical Infrastructure Technologies Ltd. provided a production and delivery schedule update for the first two units of its Nexus20 platform.
- Nexus 1 is scheduled for delivery to the South Fremantle assembly facility in late December 2025, while Nexus 2 is scheduled for early January 2026.
- Each unit will undergo a four-week final fit-out process integrating communications, surveillance, and control systems, followed by demonstrations to demonstrate commercial interest.
Key Details
- Nexus 1 Status: Military green unit; delivery to South Fremantle assembly facility expected late December 2025 for final fit-off and testing.
- Nexus 2 Status: Yellow unit with red and white mast; delivery to South Fremantle assembly facility expected early January 2026 for final fit-off and testing.
- Fit-Out Process: Upon arrival, each Nexus unit undergoes a final fit-out process of approximately four weeks.
- System Integration: The fit-out integrates advanced communications, surveillance, and control systems.
- Commercial Activity: Demonstrations will be conducted following completion, with strong commercial interest already evident across all markets.
- Product Context: The Nexus 20/24 aims to provide critical mobile telecommunications, integrated C-UAS (Counter-Unmanned Aircraft Systems), ISR (Intelligence, Surveillance, Reconnaissance), and radio for mining, defence, border security, and emergency services sectors.
Notable Quotes
- "The continued progress of the Nexus production program highlights the scalability of our platform and the global demand for rapidly deployable infrastructure solutions," said Brenton Scott, chief executive officer, Critical Infrastructure. "With production ramping up and international deployment now under way, we are entering a pivotal phase in demonstrating the versatility and capability of the Nexus system."
More from Critical Infrastructure Technologies Ltd
Jun 22, 2026 · 09:11