Cardinal Energy Ltd. Announces Monthly Dividend for September and Commencement of Steam Injection into the Reford Thermal Project

CJ · Price
Executive Summary
- Cardinal Energy Ltd. announced the commencement of steam injection at its Reford thermal oil project in Saskatchewan, marking the start of the warm-up phase prior to SAGD production.
- The company declared a cash dividend of $0.06 per common share, payable on October 15, 2025, to shareholders of record on September 30, 2025.
- Cardinal forecasts a significant production increase in Q1 2026, with total production expected to average 26,500–27,500 boe/d, driven by the Reford project ramp-up to a target of 6,000 bbl/d of heavy oil.
Key Details
- Dividend Details:
- Amount: $0.06 per common share.
- Payable Date: October 15, 2025.
- Record Date: September 30, 2025.
- Designation: Eligible dividend for Canadian income tax purposes.
- Reford Project Operations:
- Steam injection commenced on August 21, 2025.
- Construction is complete; the project is ahead of schedule and on budget.
- Current Phase: Warm-up phase via steam circulation (approx. 90 days).
- Current Output: Small quantities of oil being circulated to surface as an emulsion for processing.
- Production Target: 6,000 bbl/d of heavy oil expected in Q1 2026.
- Production Forecasts:
- Current Production: Approximately 20,600 boe/d.
- Q1 2026 Forecast: 26,500 – 27,500 boe/d (a ~30% increase).
- Future Outlook:
- Management is derisking additional thermal projects.
- Expectation to announce sanctioning of the next project when oil pricing and corporate debt conditions align.
- Product Composition (Q1 2026 Forecast vs. Current):
- Light/Medium Crude Oil: 37% (Forecast) vs. 48% (Current).
- Heavy Oil: 52% (Forecast) vs. 38% (Current).
- NGL: 3% (Forecast) vs. 4% (Current).
- Conventional Natural Gas: 8% (Forecast) vs. 10% (Current).
Notable Quotes
- "Our new Southwest Saskatchewan thermal team has brought the project in ahead of schedule and on budget."
- "Oil production is expected to slowly ramp up for the next several months until hitting the production target of 6,000 bbl/d of oil in the first quarter of 2026."