DEF 0.175 +6.1% UCU 3.63 +5.2% BBB 0.670 −1.5% PML 1.69 +1.8% GR 0.065 +0.0% GSKR 3.42 +4.0% LAR 9.08 +0.3% LSTR 0.080 +14.3% NTH 0.170 +3.0% BVA 0.800 −3.6% OTMC 0.390 +11.4% GPAC 0.355 +14.5% LEGY 0.940 +0.0% CVB 0.150 +0.0% SCZ 10.92 +7.2% ODV 3.83 +12.3% DEF 0.175 +6.1% UCU 3.63 +5.2% BBB 0.670 −1.5% PML 1.69 +1.8% GR 0.065 +0.0% GSKR 3.42 +4.0% LAR 9.08 +0.3% LSTR 0.080 +14.3% NTH 0.170 +3.0% BVA 0.800 −3.6% OTMC 0.390 +11.4% GPAC 0.355 +14.5% LEGY 0.940 +0.0% CVB 0.150 +0.0% SCZ 10.92 +7.2% ODV 3.83 +12.3%
Financings

Boreal Gold completes $57,700 private placement closing

BGLD · Price

Executive Summary

  • Boreal Gold Inc. has closed a non-brokered private placement raising a total of $57,700.
  • The financing consists of 104,000 flow-through shares at $0.30 per share and 132,500 units at $0.20 per unit.
  • Proceeds are designated for exploration activities, including ground geophysics, assay costs, and grid refurbishment across the Fay Lake, North Star, and Melgurd Lake properties.

Key Details

  • Total Gross Proceeds: $57,700.
  • Flow-Through Shares: 104,000 shares issued at $0.30 per share, generating $31,200 in proceeds.
  • Units: 132,500 units issued at $0.20 per unit, generating $26,500 in proceeds.
  • Warrant Terms: Each unit consists of one common share and one common share purchase warrant. The warrant entitles the holder to purchase one common share at an exercise price of $0.20 per warrant for a period of 24 months following issuance.
  • Hold Period: Securities are subject to a four-month statutory hold period in Canada, ending on May 1, 2026.
  • Use of Proceeds - Fay Lake:
    • Ground geophysical surveys over the western portion of the Fay Lake grid (previously uncovered) and the northeastern portion to follow the strike extension of the Sunrise conductor.
    • Assays for rock samples collected on the Fay grid, eastern extension of the Sunrise grid, and Koscielny Lake.
    • Creation of geological maps and reports detailing 2025 mapping, prospecting, and sampling work.
    • Drill testing of targets subject to confirmation of airborne conductors by ground geophysics and consultation with the Kiciwapa Cree Nation.
  • Use of Proceeds - North Star:
    • Line cutting and refurbishing of old grids (specifically lines 46 N to 59 N between baselines 46 E and Tie Line 59 E) for mapping and drilling purposes.
    • Geological remapping and detailed sampling of grids from lines 59+50 N south to L 46 N, with emphasis on the section between North Star and Gold Rock deposits.
    • Pending results from 12 samples of quartz vein material collected from muck piles and underground development (previously assayed by Foran Mining in 2004 at 0.29 oz/t Au and 0.27 oz/t Au).
  • Use of Proceeds - Melgurd Lake:
    • Assays and preparation of maps and reports from the summer 2024 mapping of the Keep Lake grid.
  • Future Plans (North Star):
    • Planned selective infill and down plunge drilling on the Gold Rock vein in 2026 to complete a resource estimate and NI 43-101 technical report.
    • Objective is to define sufficient tonnes and grade to warrant a prefeasibility study.