Gold 3,885.20 −2.9% Silver 50.05 −3.8% Copper 6.20 −1.4% Oil 88.21 +1.9% Palladium 994.00 −5.0% PRU 6.09 −3.3% NGEX 21.24 −4.2% TWO 0.370 +0.0% BIG 0.960 +1.1% VCG 1.10 +0.0% SCD 0.145 +0.0% GAL 0.372 +0.0% SAG 0.630 −4.5% VIZ 0.195 +0.0% SAGA 0.375 −6.2% ZEN 0.530 −3.6% TDG 0.490 +0.0% GDP 0.230 +0.0% PDN 8.41 +0.0% FL 0.355 −1.4% RIO 2.63 −1.5% Gold 3,885.20 −2.9% Silver 50.05 −3.8% Copper 6.20 −1.4% Oil 88.21 +1.9% Palladium 994.00 −5.0% PRU 6.09 −3.3% NGEX 21.24 −4.2% TWO 0.370 +0.0% BIG 0.960 +1.1% VCG 1.10 +0.0% SCD 0.145 +0.0% GAL 0.372 +0.0% SAG 0.630 −4.5% VIZ 0.195 +0.0% SAGA 0.375 −6.2% ZEN 0.530 −3.6% TDG 0.490 +0.0% GDP 0.230 +0.0% PDN 8.41 +0.0% FL 0.355 −1.4% RIO 2.63 −1.5%
Technical Study

Amex continues bulk sample, phase 1 feasibility work

AMX · Price

Executive Summary

  • Amex Exploration Inc. submitted a permit application for its Perron gold project bulk sample program, targeting activity commencement in H1 2026.
  • Engineering firm Evomine has been contracted to lead the Phase 1 Feasibility Study (FS) and detailed engineering, with metallurgical testing of a 120kg sample currently underway.
  • The Phase 1 FS is scheduled for release by end of Q1 2026, incorporating current gold market conditions to support permitting and a targeted 2028 project start-up.

Key Details

  • Bulk sample permit application submitted in September 2025; activities targeted for first half of 2026 pending regulatory approval.
  • Major RFQs progressing with long-lead items released; discussions ongoing with contractors, equipment/infrastructure providers, and consultants.
  • Advanced discussions underway for bulk sample milling at nearby facilities in the Abitibi region.
  • Detailed underground designs (portal, ramp, development, stopes) completed and slated for use in Phase 1 mining operations.
  • Bulk sample program intended to validate geological/mining hypotheses and gather technical data for the Perron project.
  • Evomine (Quebec-based engineering consulting firm) awarded mandate for detailed engineering design and Phase 1 FS, creating synergies between the bulk sample and development scenario.
  • 120-kilogram composite mineralized sample from the Champagne zone sent to a metallurgical laboratory in December 2025 to test compatibility with local mill flow sheets.
  • Phase 1 FS on track for completion and release by end of Q1 2026; will incorporate recent gold price increases to positively impact project economics.
  • FS will serve as a cornerstone document for project permitting and future development decisions.
  • Company targets potential project start-up in 2028 based on current timelines.
  • Perron project location: ~110 km north of Rouyn-Noranda, Que., comprising 183 contiguous claims (65.75 sq km).
  • Consolidated land package (including Perron West, Abbotsford, and Hepburn projects in Ontario) spans 501.08 sq km.
  • Infrastructure advantages: Year-round road access, 30 minutes from an airport, 6.5 km from Normetal, and proximity to major gold producer process plants.