Production / Operations
Aduro's NGP plant transitions into operating programs

ACT · Price
Executive Summary
- Aduro Clean Technologies has transitioned its Next-Generation Process (NGP) pilot plant in London, Ont., from commissioning and mechanical completion into initial structured operating campaigns.
- The facility is now conducting continuous, integrated operations to generate performance data, refine operating parameters, and validate design assumptions for the upcoming First-of-a-Kind (FOAK) industrial plant.
- FOAK development is advancing concurrently, with site selection completed and equipment evaluation underway to inform detailed engineering, design decisions, and long-lead procurement planning.
Key Details
- Transition to Operations: NGP pilot plant shifted from project execution/commissioning to structured operating campaigns following the conclusion of installation, mechanical completion, and system integration in December 2025.
- Operational Readiness: Operations and technical teams completed comprehensive training covering process operation, automation, control systems, safety procedures, and abnormal operating condition response.
- FOAK Progress: Site selection for the FOAK industrial facility is complete; equipment evaluation and testing are actively progressing to inform design and long-lead procurement.
- Data Generation & Feedstock Testing: Campaigns will evaluate mixed waste plastic samples and real-world feedstocks to assess performance across variable compositions, refine operating windows, and validate design assumptions for scale-up.
- Controls & Automation: Plant operates with an industrial-grade automation and controls architecture supplied by Siemens, enabling high-resolution data collection and direct translation of control strategies to larger-scale facilities.
- Scale-Up Pathway: The NGP pilot plant serves as the critical technical bridge between laboratory development (R2 continuous-flow reactor) and the FOAK industrial plant, feeding operational data directly into detailed engineering and execution planning.
- Timeline Context: Commissioning closeout activities across all major systems (process, utilities, automation, safety) were finalized after the October 2025 commissioning update, marking the formal shift from project execution to sustained operations.
Notable Quotes
- Ofer Vicus, CEO: "This milestone reflects disciplined execution across our engineering, operations and project delivery teams... The FOAK facility site has been selected, and the work under way in London will directly inform design and integration planning and strengthen the company's readiness to execute the next phase of scale-up."
- David Weizenbach, COO: "Postcommissioning, our focus has shifted to operating the integrated system and learning from it... These campaigns are designed to refine operating parameters for optimal yield and consistent performance across variable feedstocks while validating design assumptions for the FOAK industrial plant."