TLO 5.37 +5.7% BNKR 4.88 +1.7% GG 2.25 +3.2% MJS 0.100 +5.3% PAAS 62.54 +3.6% PE 0.230 +0.0% SGML 17.19 +4.8% LAR 10.34 −1.1% NED 0.025 +0.0% GEN 0.080 +0.0% TVI 0.060 +0.0% SKYG 0.025 −37.5% WRLG 0.660 +6.5% FFU 0.120 −7.7% LOD 0.310 +3.3% CBI 0.110 +0.0% TLO 5.37 +5.7% BNKR 4.88 +1.7% GG 2.25 +3.2% MJS 0.100 +5.3% PAAS 62.54 +3.6% PE 0.230 +0.0% SGML 17.19 +4.8% LAR 10.34 −1.1% NED 0.025 +0.0% GEN 0.080 +0.0% TVI 0.060 +0.0% SKYG 0.025 −37.5% WRLG 0.660 +6.5% FFU 0.120 −7.7% LOD 0.310 +3.3% CBI 0.110 +0.0%
Production / Operations Routine +

Ximen Mining Corp Receives Water License for Kenville Gold Project - Nelson, BC

Ximen Mining Secures Permit Milestone Amidst Liquidity Tightrope

Executive Summary
  • Ximen Mining Corp received two water licences under the Water Sustainability Act for its Kenville Gold Mine project in Nelson, BC.
  • Licences authorize groundwater extraction from a bedrock aquifer at the Venango and Election properties.
  • This approval clears a key pre-construction condition required before building the underground portal and decline.
  • Management describes this as the "final stretch" before breaking ground on the underground decline.
  • Remaining tasks include engineering design for a water retention tank system and reports on mine site building foundations and road stability.
  • Scott Kent resigned as director and officer effective immediately (April 8, 2026).
  • Recent financing activity includes amendments to private placements totaling approximately $500,000 CAD raised in late 2025/early 2026.
Material Impact
  • The water license is a positive operational milestone but was largely anticipated given the October 2025 announcement regarding "Final Requirements."
  • While progress on permits reduces execution risk, it does not address the critical liquidity position revealed in recent financial statements.
  • The resignation of director Scott Kent is minor governance news with no stated impact on operations or finances.
  • The primary materiality driver remains capital availability; operational progress without confirmed funding for construction poses a continuation risk.
  • Current cash position reported as of Dec 31, 2025 was $3,270 CAD, though recent financings should have increased this, the burn rate suggests continued need for capital.
  • The news is incremental to previous permitting updates and does not fundamentally alter the investment thesis regarding solvency or production timeline without further financing confirmation.
XIM · Price
Company Overview
  • Company: Ximen Mining Corp is a Canadian exploration and development company focused on gold properties in British Columbia.
  • Flagship Project: Kenville Gold Mine (Nelson, BC). The company holds 95% ownership of the subsidiary holding the property.
  • Project Status: Pre-construction phase; water licenses secured, engineering designs for portal/decline and retention systems pending finalization.
  • Other Assets: Brett Project (Vernon, BC) showed high-grade drilling results in Oct 2025 (79.2 g/t Au). Other properties include Treasure Mountain, Cariboo-Armelia, and various claims in the Greenwood Mining Camp.
  • Development Stage: Underground mine development requires significant capital expenditure for portal construction and decline access.
Read the original news release →