GOLD 4107.90 −1.7% SILVER 55.88 −6.1% COPPER 6.62 −1.6% OIL 95.09 +1.0% PALLADIUM 1096.50 −2.7% CIA 2.64 −0.4% BTO 7.09 −4.3% MCI 0.155 +0.0% CAN 0.065 +0.0% BLDS 0.335 +8.1% SAO 0.050 +0.0% SF 0.315 +0.0% BEA 0.055 −15.4% BMM 3.90 +11.1% AUGC 0.295 −13.2% MFG 3.34 −3.8% CDE 21.33 −7.7% CYG 0.160 −5.9% RSMX 0.100 −4.8% TUF 0.830 −5.7% GPG 0.285 −3.4% GOLD 4107.90 −1.7% SILVER 55.88 −6.1% COPPER 6.62 −1.6% OIL 95.09 +1.0% PALLADIUM 1096.50 −2.7% CIA 2.64 −0.4% BTO 7.09 −4.3% MCI 0.155 +0.0% CAN 0.065 +0.0% BLDS 0.335 +8.1% SAO 0.050 +0.0% SF 0.315 +0.0% BEA 0.055 −15.4% BMM 3.90 +11.1% AUGC 0.295 −13.2% MFG 3.34 −3.8% CDE 21.33 −7.7% CYG 0.160 −5.9% RSMX 0.100 −4.8% TUF 0.830 −5.7% GPG 0.285 −3.4%
M&A / Property Routine +

Revolve Closes Acquisition of Three-Project, 125 MW US Development-Stage Solar Portfolio

REVV · Price

Executive Summary

  • Revolve Renewable Power Corp. has completed the acquisition of three utility-scale solar development projects totaling approximately 125 MW across Illinois, New Mexico, and Wisconsin.
  • The transaction structure requires no upfront payments; instead, the company will pay a $0.02 per watt development fee upon notice to proceed with construction, plus a 10% deferred consideration tied to the project's realized sale value or fair market value.
  • Development will be funded through existing resources and strategic financing facilities, with each project advancing through permitting, interconnection, and financing milestones.

Key Details

  • Target Assets: Three utility-scale solar development projects: Henry (Illinois, 30 MW DC), Columbus (New Mexico, 56 MW DC), and Endeavor (Wisconsin, 39 MW DC).
  • Total Capacity: Approximately 125 MW of nameplate capacity.
  • Consideration & Payment Terms: $0.02 per watt development fee payable upon notice to proceed with construction; 10% deferred consideration tied to realized sale value or fair market value at notice to proceed for each individual project.
  • Upfront/Milestone Payments: None required unless an individual project proceeds to construction.
  • Funding Source: Development will be funded through the Company's existing resources and strategic financing facilities.
  • Development Framework: Each project will be advanced through permitting, interconnection, and financing milestones in accordance with Revolve's disciplined development framework, with further updates to be provided as material milestones are achieved.
  • Prior Announcement: This acquisition was previously announced on June 8, 2026.