Northwire Canada EditionFriday, July 10, 2026
Northwire
TLO 5.37 +5.7% BNKR 4.88 +1.7% GG 2.25 +3.2% MJS 0.100 +5.3% PAAS 62.54 +3.6% PE 0.230 +0.0% SGML 17.19 +4.8% LAR 10.34 −1.1% NED 0.025 +0.0% GEN 0.080 +0.0% TVI 0.060 +0.0% SKYG 0.025 −37.5% WRLG 0.660 +6.5% FFU 0.120 −7.7% LOD 0.310 +3.3% CBI 0.110 +0.0% TLO 5.37 +5.7% BNKR 4.88 +1.7% GG 2.25 +3.2% MJS 0.100 +5.3% PAAS 62.54 +3.6% PE 0.230 +0.0% SGML 17.19 +4.8% LAR 10.34 −1.1% NED 0.025 +0.0% GEN 0.080 +0.0% TVI 0.060 +0.0% SKYG 0.025 −37.5% WRLG 0.660 +6.5% FFU 0.120 −7.7% LOD 0.310 +3.3% CBI 0.110 +0.0%
Production / Operations Routine +

New Found Gold Provides Hammerdown Update

NFG · Price

Executive Summary

  • Hammerdown Gold Project remains on track for commercial production in H2/26, targeting an annual run rate of 20,000–25,000 oz Au at an all-in sustaining cost of ~US$2,500/oz.
  • Mill operations are successfully ramping up, achieving design throughput of 700 tpd and 87% gold recovery, with peak throughput reaching 1,394 tpd.
  • Grade control and resource conversion drilling is actively underway (7,000m completed of 20,000m planned), while critical infrastructure construction (civil works, crushing/sorting plants, and regrind mills) is scheduled for completion by Q3/Q4 2026.

Key Details

  • Production & Financial Targets: Commercial production expected in H2/26; anticipated run rate of 20,000 to 25,000 ounces of gold per year; all-in sustaining cost (AISC) of approximately US$2,500 per ounce.
  • Mill Performance & Throughput: Design criteria of 700 tpd achieved; peak throughput reached 1,394 tpd; gold recovery averaging ~87% (targeting ~92% post-circuit conversion from flotation-Merrill-Crowe to gravity-CIL).
  • Mining & Grade Control: Overburden stripping for Phase I pit completed in Q1/26; main access ramp established; delivery of mineralized material meeting 700 tpd design criteria; continuous improvements in head grade delivered to the Mill.
  • Drilling Programs: 20,000m of 5x5m grid-based grade control drilling commenced early Q2/26 (7,000m completed to date); 10,000m mineral resource conversion/condemnation program planned for 2026 to support Phase II pit mining (scheduled 2028) and inform a 2027 resource estimate update.
  • Infrastructure & Construction: Civil works completion scheduled for end of Q3/26; permanent crushing and sorting plant construction scheduled for end of Q4/26; new regrind mills construction/engineering ongoing with commissioning targeted for Q4/26.
  • Workforce & Safety: 50 new personnel hired to end of Q2/26, with 14 additional hires scheduled for June; 40 new jobs created to date; >90% of new hires sourced from Newfoundland; total workforce of 264 (76 employees, 188 contractors); zero lost time incidents and TRIF of 0 after >105,000 person-hours worked in 2026.
  • Management Appointments: Mark Ross, P.Geo., appointed as General Manager, Mines, bringing 20+ years of experience in mine geology and technical services.

Notable Quotes

  • "We continue to make steady progress towards our objective of achieving commercial production at Hammerdown in H2/26, where we anticipate a run rate of 20,000 to 25,000 ounces of gold produced per year at an all-in sustaining cost of approximately US$2,500 per ounce, in line with our recently completed preliminary economic assessment." – Keith Boyle, CEO
  • "Since completing the Hammerdown acquisition, we have put the people and processes in place and are continuing to commission the necessary infrastructure." – Keith Boyle, CEO
Read the original news release →

More from New Found Gold Corp.