Gold 3,668.50 +3.8% Silver 43.70 +9.1% Copper 5.52 +3.4% Oil 83.33 −0.4% Palladium 879.00 +5.5% MUN 0.285 +11.8% RNCH 0.030 +0.0% GSKR 2.30 +8.0% ADY 0.370 +5.7% TSK 0.640 +1.6% BAY 0.055 +22.2% CGNT 0.670 −2.9% INFI 0.190 +0.0% GSS 0.045 +50.0% HAY 0.040 +0.0% WRLG 0.430 +1.2% MPVD 0.015 + GGO 0.980 +5.4% NAU 0.530 +6.0% COCO 0.260 +8.3% TBLL 0.045 +12.5% Gold 3,668.50 +3.8% Silver 43.70 +9.1% Copper 5.52 +3.4% Oil 83.33 −0.4% Palladium 879.00 +5.5% MUN 0.285 +11.8% RNCH 0.030 +0.0% GSKR 2.30 +8.0% ADY 0.370 +5.7% TSK 0.640 +1.6% BAY 0.055 +22.2% CGNT 0.670 −2.9% INFI 0.190 +0.0% GSS 0.045 +50.0% HAY 0.040 +0.0% WRLG 0.430 +1.2% MPVD 0.015 + GGO 0.980 +5.4% NAU 0.530 +6.0% COCO 0.260 +8.3% TBLL 0.045 +12.5%
Production / Operations Material −

Nickel 28 Releases Ramu Q3 2026 Operating Performance

Nickel 28 reports that third-quarter operating costs doubled as a surge in sulphur prices significantly compressed its profit margins.

Executive Summary

Nickel 28 Capital Corp. (NKL) released third-quarter 2026 operational results for its 8.56% joint-venture interest in the Ramu Nickel-Cobalt operation in Papua New Guinea. Production, shipment, and inventory figures are reported on a 100% Ramu basis, rather than Nickel 28’s attributable share. The release serves as an operational update and does not include company-level revenue, net income, cash flow, cash balance, debt balance, or an updated capital structure. The figures are unaudited and subject to local and corporate audit review, with the company cautioning that the financial information is preliminary and may change materially.

Nickel 28 reported contained nickel production of 9,043 tonnes in MHP for Q3 2026, a decrease of 2.2% from 9,242 tonnes in Q3 2025. Contained cobalt production reached 929 tonnes, an increase of 4.7% from 887 tonnes. Nickel sales totaled 7,403 tonnes, down 25% year over year from 9,880 tonnes. Cobalt sales were 775 tonnes, down 18% from 948 tonnes. The company attributes the decline in sales primarily to the timing of a shipment not recognized in the quarter. Nickel inventory rose to 2,734 tonnes at September 30, 2026, from 1,094 tonnes at June 30, 2026. Management expects the timing difference to reverse in the following quarter.

The LME average nickel price was US$7.52/lb in Q3 2026, up 10% year over year from US$6.81/lb. The average cobalt price was US$24.41/lb, up 58% from US$15.48/lb. Production costs, net of by-product credits, were US$6.15/lb of nickel produced in MHP, compared with US$3.07/lb in Q3 2025. Year-to-date 2026 production costs were US$4.25/lb, compared with US$3.27/lb in the prior-year period. The company attributed the cost increase primarily to higher sulphur prices, a major consumable in the HPAL process, as well as lower average nickel and cobalt prices during the quarter versus the first half of 2026.

Nickel capacity utilisation was 111% of design capacity in Q3 2026, versus 113% in Q3 2025. Year-to-date utilisation was 107%. Year-to-date 2026 production was 26,062 tonnes of contained nickel and 2,595 tonnes of contained cobalt. To meet the prior 2026 guidance of approximately 33,100 tonnes of nickel and 3,100 tonnes of cobalt, Q4 would need about 7,038 tonnes of nickel and 505 tonnes of cobalt, which appears achievable at the current run-rate.

Material Impact

Nickel 28 Capital Corp. (NKL) reported a sharp deterioration in the economics of its Ramu mine in the third quarter of 2026, driven primarily by a surge in unit costs that has significantly compressed margins. While production reliability remained intact—with nickel output only modestly lower year over year, cobalt production increasing, and capacity utilization staying above design levels—the financial performance of the asset has weakened considerably.

The critical issue is the rapid escalation in production costs. Q3 2026 production cost reached US$6.15/lb, more than doubling from US$3.07/lb a year earlier and rising 28% from US$4.81/lb in Q2 2026. The trajectory of costs has been consistently deteriorating, moving from US$2.81/lb in Q1 2026 to US$4.81/lb in Q2, and finally to US$6.15/lb in Q3. This figure came in well above the H1 2026 average of US$3.78/lb, confirming prior company warnings that higher sulphur prices would pressure H2 2026 margins. The magnitude of the increase represents a material step-down in cash generation rather than a mere directional warning.

Using the Q3 nickel price of US$7.52/lb and the Q3 cost of US$6.15/lb, the implied margin is only about US$1.37/lb before depreciation, corporate costs, and tax. This compares with about US$3.43/lb in Q2 2026 and about US$5.07/lb in Q1 2026, indicating severe margin compression. Prices were supportive year over year but weaker sequentially; nickel fell from US$8.24/lb in Q2 2026 to US$7.52/lb in Q3, while cobalt fell from US$25.65/lb to US$24.41/lb. The combination of lower sequential prices and sharply higher costs forms the core of the negative outcome.

Sales performance was largely affected by timing rather than production failure. However, inventory built from 1,094 tonnes to 2,734 tonnes, tying up working capital and delaying cash receipts. The release did not quantify Q3 net income, cash flow, or debt, so the cash impact must be inferred from the per-pound margin and sales timing. On that basis, the quarter is materially weaker than H1 2026.

Prior-period context shows the company generated strong H1 2026 results, received a US$4.4 million distribution, and repaid US$8.2 million of construction debt in October 2026, reducing the attributable debt balance to about US$24.5 million. Q3’s margin compression puts future distribution and repayment capacity under pressure if costs persist.

NKL · Price
Company Overview

Nickel 28 Capital Corp. (NKL) is listed on the TSXV and the FSE under ticker 3JC0. The company is a nickel-cobalt producer through its 8.56% joint-venture interest in the producing Ramu Nickel-Cobalt operation in Papua New Guinea. Ramu is operated by the Metallurgical Corporation of China. The integrated operation includes the Kuroumbukari mine site, the Basamuk processing plant, a 134 km pipeline and access to Lae port. It has been in operation since 2012 and has produced at or above nameplate capacity since 2017.

Nickel 28’s 8.56% interest increases automatically to 11.3% once its attributable non-recourse construction debt is repaid. The company also holds an option to acquire an additional 9.25% interest at market value, which could bring the total interest to 20.55%. The proposed Ramu Phase II expansion would approximately double production capacity at an estimated cost of US$1.6 billion. It is subject to PNG mining leases and permits. Under the JV agreements, MCC must offer to buy minority interests at fair market value, or minority partners can fund their pro-rata share. Non-funding partners face dilution.

Ramu reserves as of December 31, 2025 were 76 Mt at 0.87% nickel and 0.09% cobalt, supporting an estimated mine life of about 20 years at current production rates. Measured and indicated resources were 205 Mt at 0.86% nickel and 0.08% cobalt. The Ramu resource and reserve estimates were prepared under JORC guidelines, not NI 43-101. The company discloses that caveat.

Nickel 28 also manages a portfolio of 10 royalties on development and exploration projects in Canada, Australia and Papua New Guinea. Named royalties include Dumont at 1.75% NSR, Turnagain at 2.0% NSR, Flemington at 1.5% GRR, Nyngan at 1.7% GRR, Sewa Bay at 5% FOB GRR, Professor & Waldman at 2% cobalt NSR, North Canal at 2% cobalt NSR and Sunset at 2% cobalt NSR. Ramu is a joint-venture interest, not a royalty. The royalty portfolio is separate and does not currently generate the same level of cash flow as Ramu.

Read the original news release →