Silver X Reports Third Quarter 2026 Results and Provides Nueva Recuperada Expansion Update
Silver X delays 1,000 tpd production to 1Q27 and withdraws its 2029 growth target as the third quarter swings to a loss.

Silver X Mining Corp. (AGX) reported third-quarter 2026 net operating revenue of $10.1 million, a 103% increase year-over-year but a 42% decline from the $17.3 million recorded in the second quarter. Operating income stood at $1.4 million, compared to $0.5 million in the same period last year and $7.5 million in Q2 2026. Adjusted EBITDA was $1.0 million, up from $0.1 million in Q3 2025 and down from $6.9 million in the prior quarter. The company posted a Q3 net loss of $1.7 million, contrasting with a $0.3 million net loss in Q3 2025 and a $3.1 million net income in Q2 2026. For the first nine months, net income remained positive at $6.0 million on $40.8 million in revenue.
Production metrics showed ore processed at 54,681 tonnes, a 63% year-over-year increase but a 12% sequential decrease. Silver equivalent (AgEq) production reached 225,237 ounces, up 35% year-over-year and down 20% from the previous quarter. Plant throughput averaged 594 tonnes per day (tpd) in Q3, down from 684 tpd in Q2. Post-quarter operations saw throughput at 598 tpd in October and 709 tpd from November 1-15, both figures remaining below the 1,000 tpd target.
Costs rose during the period, with cash costs increasing to $37.97 per AgEq ounce from $34.33 in Q2, and all-in sustaining costs (AISC) rising to $49.01 per AgEq ounce from $46.10. On a per-tonne processed basis, cash costs were $156.41 and AISC was $201.87. The Recuperada expansion to 1,000 tpd has been delayed due to mechanical issues and lower metallurgical recoveries, particularly for lead, zinc, and gold. Management now expects to sustain 1,000 tpd production in the first quarter of 2027. Additionally, the company withdrew its prior 2029 target, stating it "no longer considers 2029 a reliable date for reaching 3,000 tpd and annual production of more than six million AgEq ounces."
Financial position improved significantly, with cash at $43.3 million and working capital at $26.7 million as of September 30, 2026. This contrasts with $10.1 million in cash and a $5.7 million working-capital deficit at December 31, 2025. The improvement primarily reflects $46.6 million in net proceeds from the March 2026 10% convertible debenture.
The updated measured and indicated resource stands at 10.4 million tonnes at 202 g/t AgEq for 67.3 million ounces of AgEq, including 38.8 million ounces of silver. The inferred resource is 21.6 million tonnes at 260 g/t AgEq for 184.3 million ounces of AgEq, including 120.1 million ounces of silver.
Silver X Mining Corp. (AGX) has reset its operational guidance, pushing the timeline for sustained 1,000 tonnes per day (tpd) production from the third or fourth quarter of 2026 to the first quarter of 2027. The company also withdrew its previous 2029 target of 3,000 tpd and 6+ million ounces of silver equivalent (AgEq).
The shift follows a severe financial swing in the third quarter. Revenue fell 42% quarter-over-quarter (QoQ), while operating income dropped 81% QoQ. Adjusted EBITDA declined 85% QoQ, and net income swung from a profit of $3.1 million to a loss of $1.7 million.
Unit costs moved unfavorably on a per-ounce basis. Cash costs rose 10.6% QoQ and all-in sustaining costs (AISC) increased 6.3% QoQ, even as AISC per tonne improved. The company warned that lower throughput and recoveries are expected to negatively impact fourth-quarter production and unit costs.
The stock had already declined significantly ahead of the release. Shares closed at C$0.79 on August 6, 2026, following the prior earnings report, and fell to C$0.53 on November 25, 2026, a decline of approximately 33%. Since the October 8 production release, the stock dropped from C$0.89 to C$0.53, a decrease of about 40%.
Silver X Mining Corp. (TSXV: AGX) is a TSXV-listed silver-gold producer operating the Nueva Recuperada project in Huancavelica, Peru. The company’s land package spans 20,795 hectares and comprises three mining units alongside more than 200 exploration targets. Tangana serves as the producing mining unit, feeding the Recuperada plant, while Plata is a development unit containing the Plata veins and the Blenda Rubia bulk-tonnage deposit. Red Silver is designated as a high-grade resource definition asset, and Pampas is a recently acquired gold-silver exploration project located approximately 40 km from Nueva Recuperada.
The company currently holds no mineral reserves. Its 2025 preliminary economic assessment (PEA) includes Inferred resources, meaning the production profile and economics carry elevated technical and economic uncertainty. The company’s growth strategy involves expanding the Recuperada operation from 720 tonnes per day (tpd) toward 1,500 tpd, restarting Plata, developing Red Silver and Blenda Rubia, and integrating Pampas. A Q3 release indicated that the first step of this expansion, targeting 1,000 tpd, is behind schedule.