IMPACT Silver Corp. (IPT) reported financial results for the third quarter and the first nine months of 2026, ending September 30, 2026. Consolidated revenue for the quarter reached $18.5 million, a 73% increase from the $10.7 million recorded in the same period of 2025. Gross profit rose sharply to $7.8 million, compared to $0.5 million in Q3 2025. The company reported a net loss of $3.3 million, or $0.01 per share, for the quarter, which included a $4.3 million non-cash impairment loss associated with the Plomosas project.
For the first nine months of 2026, year-to-date revenue totaled $71.6 million, up from $31.2 million in 2025. Year-to-date gross profit was $36.9 million, versus $3.7 million in the prior year period. The company posted a year-to-date net income of $10.9 million, or $0.03 per share, contrasting with a net loss of $2.7 million in 2025. As of September 30, 2026, cash holdings stood at $53.3 million, an increase from $23.7 million at December 31, 2025. Working capital was reported at $50.0 million, and the company holds no long-term debt.
Production at the Zacualpan mine drove the quarter’s performance. Mill throughput increased 8% year over year to 38,116 tonnes. The average silver head grade rose 25% to 197 g/t, contributing to a 40% increase in silver production to 210,691 oz. Silver sales reached 208,146 oz, a 43% increase, supported by a realized silver price of $63.53/oz, up 49% from $42.65/oz in the prior year period. Operating expenses per silver-equivalent ounce produced decreased 15% to $32.61. Zacualpan generated $17.3 million in revenue and $9.8 million in gross profit for the quarter.
Year-to-date metrics at Zacualpan showed continued strength. Silver production rose 56% to 693,889 oz, while the average head grade increased 39% to 219 g/t. Operating expenses per AgEq oz produced fell 9% to $29.57. Year-to-date gross profit at Zacualpan was $42.8 million, compared to $6.4 million in 2025.
The Plomosas zinc mine was placed on care and maintenance on October 13, 2026. As of September 30, 2026, no third-party feed arrangements were in place that could economically support continued production. Consequently, a $4.3 million non-cash impairment was recorded in the third quarter of 2026.
Looking ahead, IMPACT Silver plans to upgrade and restart the 200 tonnes per day Capire mill at an estimated cost of US$5.0 million. The project is targeted for start-up in summer 2027 and will process gold-silver-copper mineral from the Noche Buena Complex. The company intends to fund the project from working capital.
Impact Silver Corp. (IPT) reported third-quarter results that confirm previously telegraphed outcomes, characterized by strong unit economics at the Zacualpan unit, record cash holdings, and a pre-announced impairment at Plomosas. The impairment and the decision to place Plomosas into care and maintenance were disclosed on October 13, 2026, meaning the Q3 financials do not introduce a new strategic direction.
A positive development in the report is a 15% year-over-year drop in Q3 operating expenses per silver-equivalent ounce, which reverses the cost pressure flagged in the second quarter. Conversely, the company reported a Q3 net loss and lower sequential revenue compared to Q2, driven by the suspension of operations at Plomosas. The timeline and $5.0 million cost estimate for Capire remain unchanged.
IMPACT Silver Corp. (IPT) is a Mexico-focused silver producer-explorer operating two primary projects. The Zacualpan Silver-Gold District, located in central Mexico, is 100% owned and spans over 200 km². Four underground mines and one open pit feed the 500 tpd Guadalupe processing plant. Over 20 years, the company has produced approximately 14 million ounces of silver and generated more than $322 million in revenue.
The Capire project features a 200 tpd pilot plant and an adjacent open pit located 16 km southwest of Guadalupe. The mill is undergoing upgrades for approximately US$5.0 million to process gold-silver-copper feed from the Noche Buena Complex, with start-up targeted for summer 2027.
Additionally, the company holds the Plomosas project, a high-grade zinc-lead-silver property in Chihuahua, Mexico. The 3,019-hectare site features a six-kilometre trend with copper-gold targets and includes a 225 tpd plant that is currently on care and maintenance.
While IMPACT Silver is a producer rather than a pre-revenue explorer, it does not disclose NI 43-101 reserves or resources for its producing assets in the provided materials.