GMV Minerals Announces Significantly Upgraded Mineral Resource Estimate for Its Mexican Hat Gold Deposit in Southeastern Arizona
GMV upgrades resource to 860,000 oz gold with 95% confidence at $3,600 per ounce.

GMV Minerals Inc. announced a significantly upgraded Mineral Resource Estimate (MRE) for its 100%-controlled Mexican Hat Gold Deposit in southeastern Arizona. The total Mineral Resource increased to 860,800 ounces of gold, up from 688,000 ounces reported in August 2025.
Geological confidence improved dramatically, with 95% of the total contained ounces (819,900 oz) classified as Measured and Indicated, leaving only 40,900 ounces as Inferred. The estimate incorporates 1,155 drill holes and trenches (54,845 meters), including 25 new diamond drill holes from the 2026 program.
Key assumptions include a gold price of US$3,600/oz, a 0.20 g/t cut-off grade, and a conceptual open-pit model with a 2:1 strip ratio. Management highlighted that the upgrade was achieved while maintaining a virtually identical overall gold grade (~0.61 g/t) compared to the previous model.
GMV Minerals Inc. (GMV) released the expected results of its 2026 infill drilling program on November 23, 2026. The update converted 95% of the resource from Inferred to Measured and Indicated categories, a shift that de-risks the geological model and validates the continuity of mineralization.
The analysis utilized a gold price assumption of US$3,600/oz. This figure is higher than the Preliminary Economic Assessment (PEA) base case of US$2,500/oz but remains below the PEA’s sensitivity case of US$4,000/oz. The assumption reflects current market conditions, though it introduces sensitivity risk if gold prices revert.
While the resource size and confidence have improved, the release does not alter the project's capital requirements, mine plan, or production timeline. The data serves as a foundational update to support the next stage of engineering studies.
GMV’s stock has declined from a 52-week high of $0.28 to $0.10, reflecting broader market conditions and the pre-revenue nature of the asset. The news aligns with prior management guidance and investor expectations.
GMV Minerals Inc. is a pre-revenue gold exploration and development company focused on the Mexican Hat Gold Project in Cochise County, southeastern Arizona. The project is a structurally controlled, low-sulphidation epithermal gold deposit hosted in oxidized Tertiary volcanic rocks.
The 2025 PEA outlines a straightforward open-pit heap-leach operation with a 10-year mine life, producing approximately 60,000 ounces of gold annually. Base case economics at US$2,500/oz Au project a pre-tax IRR of 66.1%, a pre-tax NPV of US$390.2 million, and a payback period of 1.53 years. Processing involves crushing ore to ~4cm topsize, conveyor stacking onto a heap leach pad at ~10,000 tonnes per day, and gold recovery via carbon adsorption.