SONORO ANNOUNCES COMPLETION OF GEOTECHNICAL PROGRAM AND INITIATION OF ADVANCED ENGINEERING FOR PROPOSED CERRO CALICHE GOLD OPERATION
Sonoro completes geotechnical studies and begins advanced engineering for the Cerro Caliche heap leach operation.

Sonoro Gold Corp. announced the completion of a comprehensive geotechnical investigation program for its Cerro Caliche gold project in Sonora, Mexico. The company has initiated the advanced engineering phase for a proposed open-pit, heap-leach mining operation.
BBA Consultants International LP provided technical oversight for the geotechnical work, which included geophysical surveys, borehole drilling, test pit excavations, and permeability testing across the proposed heap leach pad, solution ponds, crushing plant, and waste rock areas. Ausenco Mexico S. de R.L. de C.V. has been engaged as the lead engineering consultant to define site infrastructure, operational design criteria, and construction requirements.
The heap leach facility (HLF) design is expected to be finalized by the end of Q1 2027, providing critical technical inputs for the feasibility study, permitting, and updated economic assessments. Management highlighted that this work de-risks the project while the company continues a successful 50,000-meter drilling program at the newly acquired Diana and Batamote concessions.
Sonoro Gold Corp. (SGO) announced a standard progression in the feasibility study and permitting timeline for its Cerro Caliche project. The company engaged reputable engineering firms Ausenco and BBA and completed a geotechnical program, actions that validate the technical roadmap without introducing new financial or operational surprises.
This development aligns with the company's stated schedule and prior announcements regarding the 2026 PEA and permitting phase. It confirms that the HLF design will be ready by Q1 2027, a prerequisite for finalizing the feasibility study and securing construction financing.
Sonoro Gold Corp. is a Canadian exploration and development company focused on the Cerro Caliche gold project in Sonora, Mexico. The company’s flagship asset is Cerro Caliche, a low-sulphidation epithermal vein system featuring more than 25 northwest-trending gold mineralized zones. The project is currently in the permitting phase for an open-pit, heap-leach operation designed to target an initial 10-year mine life at a processing rate of 16,000 tonnes per day.
An economic study released in April 2026, a preliminary economic assessment (PEA), indicates a pre-tax net present value (NPV8) of $360 million and an internal rate of return (IRR) of 65% at a gold price of $3,500/oz, with an initial capital expenditure (CAPEX) of $83 million. Sonoro Gold also holds the San Marcial gold-silver project, which is currently under evaluation for a potential spin-out to unlock value. The company’s property footprint has expanded to over 8,600 hectares through recent acquisitions, providing significant exploration upside.