Honey Badger Silver Receives Positive Mill Restart Assessment for PC Silver Mine
Honey Badger’s mill restart assessment validates a staged, lower-capital path to production at the PC Silver Mine.

Honey Badger Silver Inc. (TUF) announced the results of a comprehensive condition assessment and phased restart plan for its 100%-owned PC Silver Mine, prepared by Tusk Automation Inc. The assessment confirmed that the existing processing plant is in good condition with no barriers to restart.
The Board has approved Phase 1 of the restart plan, which focuses on refurbishing the existing crushing circuit at an estimated cost of C$1.8 million, targeting completion during the 2026-2027 winter season. Phase 2, covering grinding, flotation, and dewatering, is estimated at C$12.6 million, with a target commissioning date of late 2027. Phase 3, involving full production systems, is estimated at C$21.2 million, targeting completion by July 2028. The total indicative program cost for the staged restart is approximately C$43.7 million.
Production is targeted at 1,000 tonnes per day (tpd) by mid-2028. These estimates exclude underground mine development, water treatment, paste backfill, and other ancillary site costs. The company will continue technical studies, project engineering, and evaluate opportunities to integrate existing infrastructure into the broader development strategy.
Honey Badger Silver Inc. (TUF) has released a report from Tusk Automation that validates the company’s strategy of utilizing its mothballed 1982-era processing facility to lower capital requirements and accelerate production timelines. The report outlines a C$1.8 million cost for Phase 1, a figure that stands in sharp contrast to the C$667 million pre-commercial production capital previously estimated in the September 2026 Preliminary Economic Assessment (PEA). This discrepancy reinforces the company’s approach to an initial start-up strategy that demands significantly less upfront equity or debt than a full greenfield development or complete rebuild scenario.
The assessment confirmed that key equipment, including crushers, conveyors, grinding, and dewatering systems, is in good condition. This finding materially de-risks the execution timeline and reduces technical uncertainty for the initial production phase. The news aligns with the September 2026 PEA and the company’s engagement of Tusk Automation in September 2026, providing concrete capital and timeline parameters for the first phase of operations. This development transforms a strategic concept into an actionable engineering plan.
Honey Badger Silver Inc. (TUF) is a Canadian silver and critical minerals company focused on the development of the fully permitted PC Silver Mine in the Northwest Territories. The PC Silver Mine is a brownfield asset featuring existing infrastructure, including a 1,000 tpd mill permitted for up to 2,400 tpd, 5 km of underground development, and an airstrip, alongside advanced permitting status.
The September 2026 Preliminary Economic Assessment (PEA) outlines a 22-year mine life with an after-tax internal rate of return (IRR) of 29% and negative all-in sustaining costs (AISC) net of by-products at long-term consensus pricing.
The company holds a portfolio of 10 properties across Yukon, NWT, and Nunavut, including the Nanisivik, Yava, Plata, and Hy projects. These assets are being evaluated for silver, zinc, lead, copper, and critical minerals such as germanium, tungsten, and antimony. Management emphasizes a strategy of maximizing net present value per share through infrastructure reuse, staged development, and critical mineral optionality.