Amex Gold Mining Advances Ramp Development, Commences Power Line Construction and Completes the Mechanical Garage and Ventilation Installations at Perron Gold Project
Amex’s Perron ramp reaches 200 m as the grid-power build finally gets underway.

Amex Exploration Inc. (AMX) reported that the underground main access ramp at its 100%-owned Perron Gold Project has reached 200 metres of development. The company stated that progress is steady and on time per construction plans.
Construction is now underway on the approximately 6.5-kilometre, 25 kV power line connecting Perron to the Hydro-Québec grid at Normétal. The line has a design capacity of approximately 3 MW and is sized to serve both the 40,000-tonne bulk sample and the planned Phase 1 operation.
The company noted that the mechanical garage structure is complete, the permanent underground ventilation system is installed, and the majority of bulk sample site facilities are erected and nearing completion. The bulk sample is described as fully funded, with the power line framed as dual-purpose infrastructure that avoids a second major electrical investment later.
The release contained no new assay data, resource or reserve updates, economics, financing details, or permitting decisions. The only quantitative operating datum provided was the 200 metres of ramp advance.
Amex Exploration Inc. (AMX) released an execution-progress update on November 19, 2026, marking a continuation of construction activities at its project. The site has previously been de-risked on paper by the April 13, 2026 Phase 1 Feasibility Study and on the ground by the March 30, 2026 permit package.
The company reported that 200 meters of ramp have been completed, with power line construction underway and the garage and ventilation systems finished. This follows a series of scheduled milestones: portal construction was scheduled for the week of July 6, 2026, with contractor mobilization expected in late July. By August 5, 2026, portal drill-and-blast operations were complete. On September 2, 2026, the portal was finished and the first ramp blast occurred. By September 21, 2026, 75 meters of decline had been completed, the power line right-of-way was cleared, and poles were expected to be installed in the coming weeks.
The current ramp advance implies a rate of roughly 125 meters in about eight weeks, or approximately 15-16 meters per week. This pace is considered credible against the stated target of reaching 235 meters vertically to access the high-grade Champagne Zone. The bulk sample mining horizon is now close, and the installation of ventilation means the ventilation raise is not on the critical path for the subsequent 40,000-tonne program. That program is designed to validate mining conditions, grade continuity, dilution, recovery, and reconciliation.
Two schedule observations warrant attention. The power line was originally targeted for commissioning in the third quarter of 2026, per a February 3, 2026 release, and was later softened to "later in 2026 or early 2027" on July 6. As of mid-November, it remains under construction. Until energized, the site operates on diesel generation, a cost and delay factor not quantified in the release. Additionally, the Phase 1 Feasibility Study was guided in January 2026 to end in the first quarter of 2026 but was delivered on April 13, 2026, reflecting a pattern of modest slippage.
The release does not alter the economics, reserve base, funding position, or permitting status. The market was already aware that a bulk sample and grid connection were being constructed. The underground construction sequence is holding to plan, with milestones that are physical, verifiable, and additive to the credibility of the 2027 bulk sample and 2028 Phase 1 timeline.
Amex Exploration Inc. (ticker AMX), a TSXV-listed explorer and developer formerly known as Amex Gold Mining Inc., holds the 100%-owned Perron Gold Project in Valcanton, northern Québec, located approximately 110 km north of Rouyn-Noranda. The property comprises 183 contiguous claims covering 65.72 km² and features high-grade gold, copper-rich VMS, and hybrid mineralization. The company also controls a consolidated district package of 570.94 km², including the Perron West, Abbotsford, and Hepburn properties in Ontario. Infrastructure includes year-round road access, an airport 30 minutes away, proximity to Normétal (6.5 km), and nearby mills owned by major producers, which supports the company’s toll-milling strategy.
According to an investor presentation, the project hosts a resource of 1.615 moz Au Measured & Indicated at 6.14 g/t, plus 698 koz Inferred at 4.31 g/t. A Phase 1 Feasibility Study, announced on 2026-04-13 with a technical report filed on 2026-05-28 (effective 2026-03-31), outlines a Proven & Probable resource of 1.989 Mt at 12.1 g/t for approximately 774,500 oz. The study projects an average production of 147,000 oz/yr over a five-year mine life. Key economic metrics include an All-In Sustaining Cost (AISC) of US$910/oz, operating costs of US$675/oz, and initial capital expenditure of C$193.9M, gross of C$68.1M in pre-production revenue. Sustaining capital is estimated at C$238.2M. The project yields an after-tax NPV5 of C$1.127B and an IRR of 114.6%, with an after-tax payback period of 0.5 years. The operation is designed for 1,100 t/d underground, contractor-mined, toll-milled production.
The study assumptions utilize a gold price of US$3,500/oz and an exchange rate of CAD/USD 1.38. Sensitivity analysis indicates an after-tax NPV5 ranging from C$427M at US$2,000/oz to C$1,822M at US$6,000/oz. No current gold price series was provided to test the base assumption. The development path involves a 40,000-tonne bulk sample, for which permits were received on 2026-03-30, with portal and ramp construction underway. Bulk sample operations are targeted for 2027, with Phase 1 commercial production via toll milling targeted for 2028, subject to environmental impact assessment and permitting.