CENTURY LITHIUM RECEIVES NOTICE OF COMPLETION AND ACCEPTANCE OF BASELINE STUDIES FOR ANGEL ISLAND LITHIUM PROJECT, NEVADA USA
The Bureau of Land Management has cleared baseline studies for Century’s Nevada lithium project, setting a February 2028 decision target.

Century Lithium Corp. (LCE) has received formal notice from the U.S. Bureau of Land Management (BLM) confirming that baseline data collection and reporting for the Angel Island Lithium Project are complete. The agency designated an Environmental Impact Statement (EIS) as the required level of review under the National Environmental Policy Act (NEPA).
The project is listed under the FAST-41 program, which sets a target Record of Decision date of February 4, 2028. Next steps include the preparation of a Supplemental Information Report by a third-party NEPA contractor, followed by public scoping and NEPA analyses. This announcement follows the November 3, 2026 BLM completeness determination of the Mine Plan of Operations and continues the established federal permitting trajectory.
Century Lithium Corp. (LCE) has confirmed the procedural progression of the federal NEPA process, aligning with the timeline previously outlined in the FAST-41 dashboard and earlier Bureau of Land Management communications. The designation of an Environmental Impact Statement (EIS) represents a standard regulatory step following the acceptance of baseline studies and does not introduce new financial, operational, or strategic variables to the project.
The permitting timeline remains anchored to February 4, 2028, consistent with prior guidance and the company's public commitments. This announcement serves as a procedural confirmation that validates the company's execution but does not alter the project's economics, capital requirements, or path to production. The market has already priced in this permitting progression, as evidenced by the stock trading near its 52-week low of $0.20 following the initial completeness determination in early November.
Century Lithium Corp. (LCE) is a pre-revenue development-stage company focused on the 100%-owned Angel Island Lithium Project in Esmeralda County, Nevada. The project utilizes a patent-pending chloride-based leaching process integrated with a chlor-alkali plant to produce battery-grade lithium carbonate and lithium hydroxide.
The 2026 Feasibility Study outlines a $4.01 billion after-tax NPV (8% discount) and a 27.4% IRR, with Phase 1 capital estimated at $997 million. The process generates sodium hydroxide as a co-product, which provides a significant economic credit that can offset operating costs. The company is also exploring rare earth element (REE) recovery from the leach solutions, though this is not yet included in the feasibility study economics.