VIZSLA SILVER PROVIDES UPDATE ON PANUCO PROJECT DEVELOPMENT
Vizsla’s Panuco project faces a delayed silver production start in H2 2028 due to ongoing security concerns.

Vizsla Silver Corp. (VZLA) has delayed its targeted first silver production at the 100%-owned Panuco silver-gold project in Sinaloa, Mexico, to the second half of 2028, pushing the timeline back from the previously targeted second half of 2027. The company stated that the revised schedule reflects current expectations for permitting, site readiness, and construction timing.
Construction-readiness work has progressed, with M3 Engineering & Technology completing approximately 50% of engineering and approximately 85% of the process plant equipment currently contemplated having been ordered. The company has awarded three key development contracts for EPCM, mine design, and equipment supply, with the main mining contract to be awarded “in due course.” Vizsla Silver is currently working with Mexican federal authorities and third-party security advisors to strengthen security arrangements before a phased return to site, noting that the timing of a formal return depends on security conditions.
The November 2025 Feasibility Study operating, capital, and economic parameters remain unchanged except for the revised first-production target. The study outlines the following key metrics:
- Production rate: 3,300 tpd rising to 4,000 tpd in Year 4
- Initial mine life: 9.4 years
- Average annual production: 17.4 moz AgEq
- Initial capital: US$238.7 million
- Sustaining capital: US$287.3 million
- Average cash costs: US$8.56/oz AgEq
- Average AISC: US$10.61/oz AgEq
- After-tax NPV(5%): US$1.8 billion
- IRR: 111%
- Payback: 7 months
- Price assumptions: US$35.50/oz silver and US$3,100/oz gold
The company explicitly stated that the updated development schedule does not represent an updated economic study and that the Feasibility Study economics have not been updated for the revised schedule, potential cost escalation, financing costs, or other changes. No production decision has been made, and a construction decision will only follow detailed engineering, financing arrangements, and receipt of all required permits and approvals.
Additionally, Vizsla Silver has committed an initial US$5 million contribution to the Vizsla Foundation and plans to direct a percentage of future profits toward it.
Vizsla Silver Corp. (VZLA) has confirmed a one-year delay in its first silver production timeline, shifting the key cash-flow event from the second half of 2027 to the second half of 2028. This adjustment marks a significant departure from the company’s January 2026 year-end summary and outlook, which targeted a construction decision in the second half of 2026. A subsequent update in November 2026 provided no production decision, confirmed permit receipt, or formal return to site.
Progress on engineering and procurement remains underway, with 50% engineering completion, 85% of process plant equipment ordered, and three development contracts awarded. However, these activities represent execution work ahead of a final investment decision rather than a replacement for the delayed production timeline. Additionally, the mining contract, which the April 2026 release stated would be awarded in the second quarter of 2026, is now described as still to be awarded “in due course” in the November 2026 release.
The company’s feasibility study headline numbers remain unchanged, but the release notes that net present value, internal rate of return, and payback periods have not been updated to reflect the delay, cost escalation, or financing costs. Operational challenges persist regarding the security situation; while the company has outlined preparations for a phased return to site, it has not provided a specific date. This uncertainty leaves a key operational gate open, making the H2 2028 target dependent on conditions outside the company’s full control.
The release did not include an updated capital budget, financing plan, or explanation of whether the delay alters total funding requirements. According to prior-period context from the financial statements, cash holdings were US$406.5 million at the end of the first quarter of 2026 (three months to 2026-07-31) and US$427.3 million at the end of fiscal year 2026 (twelve months to 2026-04-30), with total debt standing at US$240.4 million on the latest USD balance sheet. While liquidity is not currently an immediate crisis, the delay defers cash inflow and could increase financing needs if capital expenditure or sustaining capital expenditure rises. With no transcript provided, management’s prior verbal projections cannot be tested against the written record, on which the H2 2027 production target has been missed by a year.
Vizsla Silver Corp. (VZLA) is a Canadian development-stage company advancing the 100%-owned Panuco silver-gold project in Sinaloa, Mexico. The Panuco project serves as the company's flagship asset. A feasibility study released in November 2025 outlines a processing capacity of 3,300 tons per day, with plans to expand to 4,000 tons per day in Year 4. The study projects an initial mine life of 9.4 years and average annual production of 17.4 million ounces of silver equivalent (Moz AgEq), including 20.1 moz AgEq per year during Years 1 through 5.
Life-of-mine payable production is estimated at 94.7 moz of silver plus 776,000 ounces of gold. Initial capital requirements are listed at US$238.7 million, with sustaining capital estimated at US$287.3 million. The company remains pre-revenue. According to the latest management discussion and analysis and financial statements, the company has reported no revenue, negative operating cash flow, and losses driven largely by finance costs and corporate costs.
Regarding royalty status, no royalty or stream schedule is provided in the materials. While the release describes Panuco as 100%-owned, this designation does not independently confirm royalty-free status. There is currently no analyst coverage, target range, or consensus estimates provided in the materials, meaning a target range cannot be stated. Additionally, no investor presentation is provided; consequently, management background and strategic-investor details cannot be independently verified beyond the names and titles included in the company's releases.