Gold 3,668.50 +3.8% Silver 43.70 +9.1% Copper 5.52 +3.4% Oil 83.33 −0.4% Palladium 879.00 +5.5% MUN 0.285 +11.8% RNCH 0.030 +0.0% GSKR 2.30 +8.0% ADY 0.370 +5.7% TSK 0.640 +1.6% BAY 0.055 +22.2% CGNT 0.670 −2.9% INFI 0.190 +0.0% GSS 0.045 +50.0% HAY 0.040 +0.0% WRLG 0.430 +1.2% MPVD 0.015 + GGO 0.980 +5.4% NAU 0.530 +6.0% COCO 0.260 +8.3% TBLL 0.045 +12.5% Gold 3,668.50 +3.8% Silver 43.70 +9.1% Copper 5.52 +3.4% Oil 83.33 −0.4% Palladium 879.00 +5.5% MUN 0.285 +11.8% RNCH 0.030 +0.0% GSKR 2.30 +8.0% ADY 0.370 +5.7% TSK 0.640 +1.6% BAY 0.055 +22.2% CGNT 0.670 −2.9% INFI 0.190 +0.0% GSS 0.045 +50.0% HAY 0.040 +0.0% WRLG 0.430 +1.2% MPVD 0.015 + GGO 0.980 +5.4% NAU 0.530 +6.0% COCO 0.260 +8.3% TBLL 0.045 +12.5%
M&A / Property Routine +

Perpetua Resources Announces Non-Binding MOU with a Major American Aerospace & Defense Company to Evaluate Domestic Tungsten Opportunities

Perpetua signs non-binding tungsten MOU, adding defense validation with zero committed capital.

Executive Summary

Perpetua Resources Corp. (PPTA), through its subsidiary Perpetua Resources Idaho, Inc., has entered into a non-binding memorandum of understanding with an unnamed major aerospace and defense company. The agreement outlines the evaluation of potential funding and future supply of domestic tungsten under the company’s newly branded Industrial Tungsten Acceleration Program (I-TAP).

Under the framework terms, the counterparty could provide non-equity funding of up to $55.5 million and would have the right to acquire up to 50% of future tungsten production. However, the MOU commits neither party to any specific action. Funding is at the counterparty’s sole discretion, and there is no obligation to fund, buy or sell tungsten, or grant supply rights. Any binding arrangement would require definitive agreements, due diligence, and approvals, with the company noting there is no assurance such steps will be completed.

The scope of the program covers tungsten mineralization in the historic Stibnite Mining District and related claims. This area is explicitly separate from the approved gold-antimony mine plan and would require additional environmental review and permitting. If funded, planned work includes Phase 1 drilling, resource definition, metallurgical and processing testing, decline design, and permitting. A possible Phase 2 would involve underground exploration, a preliminary economic assessment, pilot processing, and a recovery-circuit assessment. J.P. Morgan acted as financial advisor in connection with the investment contemplated by the MOU.

Material Impact

Perpetua Resources Corp. (PPTA) has advanced its long-standing tungsten narrative with a recent memorandum of understanding (MOU) with a downstream acquisition and development counterparty. This development follows a sequence of events including the August 6, 2026, discovery of a new gold-tungsten zone and the October 26, 2026, receipt of an up-to-$40M U.S. Army DOTC award. That award, which brings total government funding to approximately $126M, was explicitly designated for tungsten exploration and a decline beneath Hangar Flats.

The strategic implication of the MOU is that it validates third-party defense-industrial interest in Stibnite tungsten. If converted, the agreement could provide non-dilutive funding and secure an end-market for a mineral the U.S. does not currently mine. Tungsten has previously appeared in drill results, such as CTFZ 21.3m @ 3.2 g/t Au + 0.9% W and Hangar Flats 9.8m @ 4.6% W + 8.3% Sb. However, these instances have been characterized as by-product curiosities in exploration holes rather than a defined resource, a component of the mine plan, or a reserve.

Financially, the potential impact is small relative to the company’s scale. The MOU offers up to $55.5M of potential, discretionary funding, which is immaterial to the core gold-antimony financing against a ~$2.576B direct capex and a ~$3.0B market cap. The agreement grants a 50%-of-tungsten-production right if exercised, which would dilute future tungsten economics but does not affect the approved gold-antimony plan.

The timing of the MOU occurs within a deteriorating financing and cash backdrop that the agreement does not address. Perpetua’s cash position has declined from $669.5M on March 31 to $574.2M on June 30, and further to $443.4M on September 30. This reduction coincides with rising quarterly burn rates of approximately $95M in Q2 and $131M in Q3. Additionally, the $2.9B EXIM loan has slipped from a Q2 2026 close to "later in 2026," and is now projected for Q1 2027. The small, non-binding tungsten MOU is strategically additive but does not de-risk the main events of the EXIM close and final investment decision (FID).

PPTA · Price
Company Overview

Perpetua Resources Corp. (Nasdaq/TSX: PPTA) is redeveloping the historic Stibnite Gold Project in Valley County, Idaho, a brownfield gold-antimony-tungsten district. The company holds approximately 4.8 million ounces of gold reserves, presented as the largest independent U.S. gold reserve, and 149 million pounds of antimony, stated as the only U.S. antimony reserve. Measured and indicated resources total approximately 1.5 million ounces of gold, with inferred resources at approximately 1.6 million ounces, alongside large exploration targets.

The production profile targets approximately 463,000 ounces of recovered gold per year in Years 1–4, with a life-of-mine average of 296,000 ounces and 106 million pounds of antimony. Production is targeted for 2029. Under a base case scenario with gold at $3,250/oz and antimony at $10/lb, the project shows an early-years NPV5% of approximately $3.46 billion and an IRR of 23.5%. Life-of-mine NPV5% is approximately $6.05 billion with an IRR of 32.3%. Average all-in sustaining costs are $498/oz in early years and $833/oz over the life of the mine. In higher gold scenarios at $4,500/oz, the NPV is approximately $6.1 billion and the IRR is 32.3%.

Permitting milestones include a Final Record of Decision in January 2025, a Final Federal Permit in May 2025, designation as a White House Priority Project in April 2025, financial assurance posting and the start of early works in October 2025, and the selection of Hatch as EPCM in December 2025.