Silverco Mining Ships First Cusi Concentrate, Provides Cusi Restart Update
Silverco shipped its first Cusi concentrate on schedule, though no grades, widths or costs were disclosed.

Silverco Mining Ltd. (SICO) shipped its first concentrate from the Cusi mine on November 16, 2026, marking an operational restart milestone that the company described as proceeding on schedule and on budget. The capital required for the restart remains unchanged at US$19.2 million. While the shipment represents a significant operational step, the company did not disclose specific details regarding tonnage, concentrate grade, payable ounces, realized or provisional prices, offtake counterparties, or unit costs for this initial shipment.
At the Cusi site, dry commissioning is complete and wet commissioning is substantially complete, with a full operational handover planned for the end of November 2026. Construction of a tailings thickener is underway, targeted for completion in January 2027, though the company noted this infrastructure is not required for current operations. Underground development continues at the Promontorio ore level, while the San Miguel ramp decline is progressing. Initial stope production at Promontorio is planned for late Q4 2026. The Cusi workforce currently consists of 142 employees and 246 contractors, with the company stating that all key hires are in place.
Cusi is designed to have a capacity of 1,200 tonnes per day, with grades and throughput expected to rise through the first half of 2027. Consequently, commercial production is now scheduled to be declared at both Cusi and La Negra in the first half of 2027. For the first time, the company provided quantified guidance for 2027, projecting combined production from Cusi and La Negra of more than 4 million ounces of silver equivalent, based on two technical reports.
Safety performance at Cusi for 2026 included one lost time incident across 577,000 exposure hours. Exploration efforts continue with a 30,000-meter program at Cusi, which is still drilling following results released on June 16, July 7, and October 14, 2026. An updated mineral resource estimate is planned for the first half of 2027.
The company reiterated its corporate goal of achieving 10 million ounces of silver equivalent production per year within three years. This follows previous Pre-Feasibility Study (PEA) framing which estimated Cusi production at approximately 2.5 million ounces of silver equivalent per year from 2028 to 2032, with an all-in sustaining cost (AISC) of US$26.75 per ounce and 90% silver revenue.
Silverco Mining Ltd. (SICO) has physically shipped concentrate from its Cusi project, converting twelve months of operational updates into a completed milestone. This development removes the primary risk associated with the restart of the past-producing asset, which previously held no reserves.
The company’s chief executive stated that Silverco now operates two silver mines in Mexico. However, both assets remain classified as pre-commercial under the company’s accounting standards. La Negra was pre-commercial as of the Q2-2026 statements, with a commercial declaration now targeted for the first half of 2027. Consequently, the assets are not yet generating revenue-recognized income.
The release provided limited financial detail, omitting concentrate tonnage, concentrate grade, payable silver, treatment and refining charges, and realized price. Without these figures, it is not possible to estimate Cusi’s Q4 revenue from the disclosure.
Management issued its first hard forecast for 2027, guiding for greater than 4 moz AgEq in production for the combined company. This figure is consistent with the presentation’s range of 4–5 moz by the end of 2027 but falls below the arithmetic implied by the two technical reports in circulation, which suggest approximately 6.6 moz at steady state (Cusi at ~2.5 moz/yr plus La Negra at 4.1 moz/yr). The guidance is defensible as a ramp-year number.
Silverco’s stock closed at C$7.83 on the date of the release, down approximately 21% from C$9.90 on the prior earnings release date of August 26, 2026. The market had already discounted the delivery, which was telegraphed by the August 4 release noting the project was 68% complete and on budget, as well as subsequent updates in September and November.
Silverco Mining Ltd. (TSXV: SICO; OTCQB: SICOF), a Vancouver-based company listed in October 2025, is pursuing a strategy to build a multi-asset primary silver producer in Mexico. The company aims to achieve production of 10 moz AgEq/yr within three years.
The company’s La Negra asset, located in Querétaro, is a 100%-owned underground silver-lead-zinc-copper skarn/CRD deposit with approximately 30 years of operating history. It features a 2,500 tpd crush-grind-float plant producing lead-silver, copper-silver, and zinc concentrates. Silverco acquired La Negra through the Nuevo Silver share exchange, which closed on May 19, 2026, in exchange for 16.8 million shares, representing approximately 31–34% of the company. At the time of acquisition, the asset was operating at approximately 55% of nameplate capacity. The company targets commercial production in the first half of 2027, with plans to unlock full throughput through dry-stack tailings and the arrival of an Epiroc fleet between the fourth quarter of 2026 and the first quarter of 2027.
Silverco also owns the Cusi asset in Chihuahua, a 100%-owned, 11,665-hectare past-producing underground Ag-Au-Pb-Zn complex. The site includes a permitted 1,200 tpd mill, grid power, and highway access. The company completed the restart to first concentrate on November 16, 2026, and is ramping up to 1,200 tpd, with commercial production targeted for the first half of 2027. The asset is designed to generate approximately 90% of its revenue from silver.
Management includes President and CEO Mark Ayranto, who brings approximately 35 years of experience, including a previous role as COO of Victoria Gold. Victoria Avila serves as CFO, effective September 30, 2026, replacing Sean Fallis. Tara Hassan is EVP of Corporate Development, having previously worked at SilverCrest. Nico Harvey serves as VP of Project Development and is the company’s non-independent qualified person, while Dr. Jesus Velador is VP of Exploration.
The board and advisory team include Gary Brown, former CFO of Wheaton Precious Metals; Gregg Bush, COO of Heliostar; Tim Sorensen; and George Paspalas, an advisor and former CEO of MAG Silver and Aurizon.