Northwire Canada EditionSaturday, October 17, 2026
Northwire
⌕
GOLD 4181.10 +0.3% SILVER 57.30 +0.3% COPPER 6.57 +0.3% OIL 99.02 +1.1% PALLADIUM 1118.60 −0.9% GBU 0.095 +0.0% ATY 0.225 +4.7% GRDM 0.215 +0.0% PPM 0.300 +0.0% GZD 0.040 −11.1% CAN 0.060 +0.0% BGF 0.025 +0.0% MSV 0.570 +0.0% CCMM 0.485 +0.0% MON 0.385 −6.1% OMI 0.245 −2.0% BUFF 0.800 +2.6% FEO 0.630 −3.1% LIB 0.710 −1.4% NPR 0.620 +0.0% QZM 0.380 +0.0% GOLD 4181.10 +0.3% SILVER 57.30 +0.3% COPPER 6.57 +0.3% OIL 99.02 +1.1% PALLADIUM 1118.60 −0.9% GBU 0.095 +0.0% ATY 0.225 +4.7% GRDM 0.215 +0.0% PPM 0.300 +0.0% GZD 0.040 −11.1% CAN 0.060 +0.0% BGF 0.025 +0.0% MSV 0.570 +0.0% CCMM 0.485 +0.0% MON 0.385 −6.1% OMI 0.245 −2.0% BUFF 0.800 +2.6% FEO 0.630 −3.1% LIB 0.710 −1.4% NPR 0.620 +0.0% QZM 0.380 +0.0%
Production / Operations Routine +

Desert Gold Advances Barani Gravity Plant Installation and Confirms July 19th, 2026 Commissioning Target at SMSZ Project, Western Mali

Desert Gold Advances Mali Plant Installation Toward July Commissioning

Executive Summary
  • The company is advancing site development at Barani East within the SMSZ Project in Western Mali.
  • A 200 tonne-per-day gravity processing plant and 650 kVA generator have been inspected in China and are currently in transit to Mali.
  • Site preparation includes clearing of approximately 52,000 square meters, foundation excavation, fencing, and access infrastructure.
  • Water supply drilling is underway with favorable hydrogeological conditions identified at depths between 60 and 90 meters.
  • Plant commissioning is targeted for mid-July 2026.
  • Equipment logistics indicate expected arrival at the Port of Dakar in mid-June 2026, with delivery to Barani site anticipated in late June 2026.
Material Impact
  • The news confirms execution progress on the capital deployment announced during the February 2026 private placement (C$7.18M).
  • This is an expected milestone following the November 2025 PEA which outlined the plant construction and commissioning timeline.
  • No new economic upside or resource expansion is disclosed in this release; it validates the operational plan rather than altering the valuation thesis.
  • The confirmation of equipment transit reduces execution risk regarding the supply chain but does not constitute a material change to the project economics previously modeled.
DAU · Price
Company Overview
  • Flagship Project: SMSZ Gold Project in Western Mali, specifically the Barani East deposit.
  • Status: Fully permitted with a completed Preliminary Economic Assessment (PEA).
  • Production Plan: Modular gravity processing plant targeting 200 tonnes per day initially, scalable to 50 tonnes per hour. Commissioning targeted for July 2026.
  • Economics: PEA indicates an after-tax NPV10% of US$61 million and IRR of 57% at a gold price of US$2,850/oz.
  • Secondary Project: Tiegba Gold Project in Côte d'Ivoire (90% interest), currently in exploration phase with soil anomalies up to 900 ppb Au.
Read the original news release →

More from Desert Gold Ventures Inc.