GoGold Advances Los Ricos South Construction
GoGold uses US$67.5M warrant proceeds to fund the LRS project, a fully funded claim advancing on schedule.

GoGold Resources Inc. (GGD) issued a construction progress update on September 22, 2026, regarding its Los Ricos South (LRS) project in Jalisco, Mexico. The company stated that construction is "moving ahead at full steam," with more than 150 contractors on site. Site clearing and earthworks are advancing at the process plant site, and all long-lead equipment orders have been placed, including the SAG mill, tailings filter, crusher, electrical switchgear, Merrill-Crowe plant, conveyors, slurry pumps, hydrocyclones, feeders, and screens.
The plant design by M3/DENM is now 90% complete, up from 85% in the August 25, 2026 release. GoGold reiterated its target for a first silver pour in the second quarter of 2028. The company reported that it has US$284 million in cash in addition to cash flow from Parral, stating the project is fully funded with no debt or additional equity required.
New quantitative disclosures include internal estimates using US$60/oz silver and US$4,200/oz gold, a maximum cash outlay in the third quarter of 2027, and the maintenance of a minimum US$130 million cash reserve throughout the build. The funding chart footnote assumes the exercise of 27.5 million outstanding warrants in November 2028 at C$3.50/warrant for net proceeds of approximately US$67.5 million, marking the first time warrant proceeds have been explicitly folded into the LRS funding plan.
Capital spent to date on the project is US$15 million. Key milestones include earthworks and underground mine plan optimization commencing in August 2026, powerline installation starting in November 2026, and concrete foundation pouring, portal development/ramp blasting, and paste plant construction beginning in January 2027. Hill-slope stabilization and Main/Abra zone mining is scheduled for March 2027, with SAG mill delivery to site in May 2027. Plant commissioning is set for January 2028. Underground contractor Cominvi is planned to mobilize to site in the fourth quarter of 2026.
The release did not provide production, cost, revenue, or cash flow data. It did not restate or revise the US$227 million initial capex figure from the 2025 feasibility study, nor did it provide LRS reserves, resources, grade, recovery, mine life, NPV, or IRR. There was no update on Parral operations or Los Ricos North technical studies.
GoGold Resources Inc. (GGD) issued a reiteration release confirming that its schedule, funding status, contractor selection, equipment orders, and design progress remain consistent with disclosures made on June 8, 2026, and August 25, 2026. The update introduces new sensitivity framing based on US$60/oz silver and US$4,200/oz gold prices, identifies a Q3 2027 peak outlay alongside a US$130 million minimum cash floor, and explicitly incorporates US$67.5 million of November 2028 warrant proceeds into its funding plan. While these elements provide de-risking optics, the warrant proceeds represent a dilution-funded cushion rather than new capital.
Market reaction to the company’s recent developments has already priced in the construction timeline. The stock closed at C$3.74 on August 12, 2026, following the Q3 FY2026 earnings date, and rose to C$4.40 on September 21, 2026, marking a gain of approximately 17.6% over that period. An intermediate peak of C$4.51 was recorded on September 3, 2026. The news regarding the construction start on August 25, 2026, was absorbed in a single trading session, with the share price moving from C$4.23 to C$4.47, a 5.7% increase.
The most significant incremental detail in the release is that the "fully funded" status relies on an internally modeled metals deck and the exercise of warrants. Neither of these factors is currently disclosed as a risk in the company's filings.
GoGold Resources Inc. (TSX: GGD; OTCQX: GLGDF), a Canadian-based silver and gold producer headquartered in Halifax, Nova Scotia, is focused on operating, developing, exploring, and acquiring projects in Mexico. Its sole producing asset is the Parral Tailings mine in Chihuahua state, a tailings reprocessing operation now in its twelfth year. The company reported record quarterly operating cash flow from the site, which has a stated remaining mine life of four to five years. By-product credits at Parral include copper and zinc alongside silver and gold.
The company’s flagship growth asset is Los Ricos South in Jalisco state. A feasibility study was completed in 2025, and all federal environmental permits have been granted. Board construction approval was secured in June 2026, with construction formally commencing on August 25, 2026. The project is a 24-month build targeting first pour in the second quarter of 2028. The facility is a bulk-tonnage underground mine featuring a process plant that includes a SAG mill, Merrill-Crowe circuit, and paste backfill plant. The internal funding model assumes prices of US$60/oz silver and US$4,200/oz gold.
Los Ricos North, also in Jalisco state, is in the exploration and development stage. The MD&A commits to completing additional technical studies to advance the project, though no technical or economic detail is provided in the supplied materials. Management’s stated goal is to become a leading mid-tier silver producer, with the Los Ricos South build serving as the transition point from a depleting tailings operation to a conventional underground mine.