Production / Operations
Mineros Profiles Initiatives to Increase Production at its Nechi Alluvial Property

MSA · Price
Executive Summary
- Mineros announced the completion and ramp‑up of its new Aurora mobile mining and recovery plant at the Nechí Alluvial Property, built at a cost of US $6.5 million.
- The Aurora Plant is expected to reach full processing capacity of 10,000 t/day (≈5,000 m³) in early Q4 2025.
- A follow‑on mobile scavenger plant project is progressing, with Phase I slated for late Q4 2025 and Phase II for early Q2 2026, which together could boost recoveries by up to 8% per plant.
Key Details
- Construction & Cost: Aurora Plant constructed throughout 2024; completed Q3 2025; total capital cost US $6.5 million.
- Ramp‑Up Timeline: Ramp‑up performed in July–August 2025; full capacity targeted for early Q4 2025.
- Capacity: Designed for 10,000 tonnes per day (≈5,000 m³) of alluvial material processing.
- Plant Specifications: Floating recovery system, 61 m long × 12 m wide, ~1,000 t weight; equipped with high‑precision GPS/control, pressure and flow recovery systems, sorting by size and gravimetric concentration, and chemical‑free dewatering.
- Debottlenecking Initiative – Mobile Scavenger Plant:
- Phase I start‑up: late Q4 2025.
- Phase II start‑up: early Q2 2026.
- Expected to increase recoveries by up to 8 % for each attached mobile mining/recovery plant.
- Management Quote: David Londoño, President & CEO, highlighted the project’s low‑cost, low‑risk nature and its alignment with sustainability, efficiency, and community benefit goals.
Notable Quotes
“The Aurora Plant and the scavenger project demonstrate Mineros’ commitment to low-cost, low-risk projects that deliver very high returns… This initiative is the result of more than a decade of dedicated work, constant innovation and a deep commitment to a mining model that generates shared prosperity.” – David Londoño, President & CEO
Materiality Assessment: Material – Positive (significant operational development expected to enhance production capacity and recovery efficiency).