S 0.140 +0.0% BNKR 4.40 −2.2% QRO 0.045 +0.0% VCT 0.075 +36.4% PPP 1.15 +0.9% LMG 0.390 +0.0% GRDM 0.140 +0.0% ABRA 13.58 −4.1% WHY 0.295 +1.7% HHH 3.94 −0.2% COS 0.060 +0.0% NOB 0.065 −23.5% MEK 0.055 +0.0% TGOL 0.105 −4.5% FCI 0.400 −7.0% SGQ 0.350 +0.0% S 0.140 +0.0% BNKR 4.40 −2.2% QRO 0.045 +0.0% VCT 0.075 +36.4% PPP 1.15 +0.9% LMG 0.390 +0.0% GRDM 0.140 +0.0% ABRA 13.58 −4.1% WHY 0.295 +1.7% HHH 3.94 −0.2% COS 0.060 +0.0% NOB 0.065 −23.5% MEK 0.055 +0.0% TGOL 0.105 −4.5% FCI 0.400 −7.0% SGQ 0.350 +0.0%
Production / Operations

Minnova further amends omnibus incentive plan

MCI · Price

Executive Summary

  • Shareholders approved amendments to Minnova Corp.’s omnibus long‑term incentive plan (LTIP).
  • The company outlined a two‑stage technical program for the PL gold mine, targeting expanded resources, an updated NI 43‑101 resource estimate and a Class 3 feasibility study by 2026.
  • ABGM will lead the work, delivering detailed mining designs, capital & operating cost models, and a final technical report to support future financing.

Key Details

  • LTIP Amendment: Approved at the annual shareholders’ meeting; pending TSX‑V exchange approval before filing on SEDAR+.
  • PL Gold Mine Overview: Advanced‑stage project with 1,000 t/d processing plant, >7,000 m of underground ramp development and a valid underground mining permit.
  • 2025–2026 Work Program:
  • Diamond drilling to expand resources and upgrade reserves.
  • Updated NI 43‑101 mineral resource estimate.
  • Revised mine development plan prioritizing lower‑cost open‑pit mining.
  • New metallurgical testwork (ore sorting, gravity recovery).
  • Comprehensive feasibility study slated for completion in 2026.
  • ABGM Scope – Stage 1 (Mining Concept Development):
  • Audited drilling database and updated geological/resource models.
  • NI 43‑101‑compliant resource estimate.
  • Internal mining concept study report and roadmap to Stage 2.
  • ABGM Scope – Stage 2 (Class 3 Feasibility Study):
  • Detailed open‑pit and underground mine designs, 3‑D mine plan & schedule.
  • Mine engineering, infrastructure layout, basic engineering.
  • NI 43‑101‑compliant mineral reserves estimate.
  • Capital and operating cost estimates, financial models.
  • Final NI 43‑101 technical report and feasibility study.
  • Management Quote: CEO Gorden Glenn emphasized the two‑stage approach as essential for securing development funding and restarting the mine.

Notable Quotes

“The structured, two-stage approach being executed by ABGM is precisely what is needed to move the PL gold mine forward…to secure development funding and execute on our vision of restarting the mine.” – Gorden Glenn, President & CEO


Materiality Assessment: Non‑Material – Positive (operational roadmap without immediate financial impact).