Northwire Canada EditionSaturday, July 25, 2026
Northwire
B 0.150 +0.0% IFOS 2.28 −2.6% IMM 0.060 +0.0% ROCK 3.38 −1.7% NVX 0.250 −7.4% HAR 0.050 +0.0% YGT 0.175 +0.0% GEN 0.070 −nan% CRB 0.040 +14.3% MSA 7.07 +2.2% AEM 204.81 +0.7% OPW 0.105 +5.0% GRL 0.275 −1.8% AIS 0.150 +0.0% CUU 0.580 −1.7% SOMA 0.720 +5.9% B 0.150 +0.0% IFOS 2.28 −2.6% IMM 0.060 +0.0% ROCK 3.38 −1.7% NVX 0.250 −7.4% HAR 0.050 +0.0% YGT 0.175 +0.0% GEN 0.070 −nan% CRB 0.040 +14.3% MSA 7.07 +2.2% AEM 204.81 +0.7% OPW 0.105 +5.0% GRL 0.275 −1.8% AIS 0.150 +0.0% CUU 0.580 −1.7% SOMA 0.720 +5.9%
Technical Study

INTEGRA DELIVERS ROBUST FEASIBILITY STUDY FOR DELAMAR GOLD-SILVER HEAP LEACH PROJECT HIGHLIGHTING IMPROVED ECONOMICS AND REDUCED DEVELOPMENT RISK

ITR · Price

Executive Summary

  • Integra Resources released a full Feasibility Study (FS) for the DeLamar Gold‑Silver Heap Leach Project, showing an after‑tax NPV5% of $774 M (base case) to $1.7 B (spot prices) and IRR of 46%–89%, with a rapid 1.8‑year payback.
  • The FS confirms a 10‑year mine life producing ~1.1 Moz AuEq at average cash cost of $1,179/oz AuEq and AISC of $1,480/oz AuEq; total initial capital is $389 M with sustaining capex of $305 M.
  • The study adds a simplified two‑heap leach layout, expands mine life via stockpile material, and highlights strong early free cash flow ($165 M average Y1‑5) plus extensive tribal partnerships and community job creation (≈300 permanent jobs).

Key Details

  • Economic Highlights
  • After‑tax NPV5%: $774 M (base case $3,000/oz Au, $35/oz Ag); $1.7 B at spot $4,250/oz Au, $60/oz Ag.
  • After‑tax IRR: 46% (base) – 89% (spot).
  • Payback period: 1.8 years (base), down to 1.1 years at spot prices.
  • NPV‑to‑Capex ratio: 2.0 (base) – 4.4 (spot).

  • Production & Reserves

  • Mine life: 10 years active mining + 2 years residual leaching.
  • Total LOM production: 1.1 Moz AuEq (average 106 koz AuEq/yr).
  • Proven & Probable reserves (oxide only): 119.97 Mt ore @ 0.33 g/t Au, 13.56 g/t Ag → 1,259 koz Au and 52,305 koz Ag.

  • Capital Expenditure

  • Initial capex: $389 M (incl. $38 M owners’ cost).
  • Sustaining capex (Y1‑10): $305 M.
  • Total project capital (including reclamation & bonding): $747.5 M.

  • Operating Costs

  • Site‑level cash cost (co‑product): $1,179/oz AuEq.
  • AISC (co‑product): $1,480/oz AuEq.
  • Mining cost: $2.51/t mined; processing cost: $4.91/t processed; G&A: $1.51/t processed.

  • Free Cash Flow

  • Average Y1‑5 after‑tax free cash flow: $165 M (average $142.8 M per year).
  • Total net free cash flow (Y1‑10): $1,066 M.

  • Infrastructure & Power

  • Required power: up to 6.5 MW via refurbished 69‑kV line and new substation; 2 MW backup generator.
  • Two heap leach pads (Florida Mountain & DeLamar) with two‑stage crushing, Merrill‑Crowe processing (~1,360 m³/h).

  • Royalties

  • Net smelter returns: 2.5% (Triple Flag) reduced to 1.0% after C$10 M paid; 1.5% (Wheaton Precious Metals).
  • Effective average royalty rate: ~2.3%.

  • Community & Tribal Engagement

  • Relationship Agreement with Shoshone‑Paiute Tribes; ongoing discussions with additional tribes.
  • Expected creation of ≈300 permanent jobs for the life of the project.

  • Next Steps

  • Permitting advancement (NEPA, Idaho state, BLM) slated for 2026‑27.
  • Detailed engineering and financing plans to be refined; construction decision pending permitting and funding.

Notable Quotes

“The Feasibility Study confirms what we have long believed: DeLamar is one of the most compelling, resilient, and capital‑efficient heap leach gold‑silver projects in the U.S.… The FS outlines a simplified, phased, and materially de‑risked development plan with outstanding economics, including a rapid 1.8‑year payback…” – George Salamis, President & CEO


The technical report supporting this Feasibility Study will be filed on SEDAR+ within 45 days of this release.

Read the original news release →

More from Integra Resources Corp.