S 0.140 +0.0% BNKR 4.40 −2.2% QRO 0.045 +0.0% VCT 0.075 +36.4% PPP 1.15 +0.9% LMG 0.390 +0.0% GRDM 0.140 +0.0% ABRA 13.58 −4.1% WHY 0.295 +1.7% HHH 3.94 −0.2% COS 0.060 +0.0% NOB 0.065 −23.5% MEK 0.055 +0.0% TGOL 0.105 −4.5% FCI 0.400 −7.0% SGQ 0.350 +0.0% S 0.140 +0.0% BNKR 4.40 −2.2% QRO 0.045 +0.0% VCT 0.075 +36.4% PPP 1.15 +0.9% LMG 0.390 +0.0% GRDM 0.140 +0.0% ABRA 13.58 −4.1% WHY 0.295 +1.7% HHH 3.94 −0.2% COS 0.060 +0.0% NOB 0.065 −23.5% MEK 0.055 +0.0% TGOL 0.105 −4.5% FCI 0.400 −7.0% SGQ 0.350 +0.0%
Production / Operations

F3 Uranium starts EM surveys at Broach Lake

FUU · Price

Executive Summary

  • F3 Uranium Corp. has begun a high‑resolution stepwise moving‑loop electromagnetic (SWMLEM) survey covering ~65 km of priority ground at the Broach Lake property within its 100% owned Patterson Lake North project.
  • The survey targets the Tetra zone conductor and the area between Tetra and historic drill hole PAT‑16‑002 to improve targeting and reduce the number of required drill holes.
  • The program follows earlier successful EM work, geochemical sampling (423 ppm U over 0.5 m), and drilling that identified high‑grade uranium intervals in the Tetra zone.

Key Details

  • Survey Scope: ~65 km of stepwise moving‑loop electromagnetic (SWMLEM) lines on a 200 m spaced grid, covering a 1,600 m strike length that includes the ~1,200 m corridor between the Tetra zone and drill hole PAT‑16‑002.
  • Objective: Detect subtle basement‑hosted conductors beneath highly conductive overburden to increase confidence in conductor location and lower drilling inventory.
  • Historical Context:
  • Aug 5 2025 – Intercepted a 67.0 m total composite radioactivity zone at Tetra.
  • July 21 2025 – Maiden geochemical assay from PAT‑16‑002 returned 423 ppm U over 0.5 m.
  • Feb 11 2025 – Initiated exploration program with a 41 km moving‑loop time‑domain EM (MLTDEM) survey.
  • Mar 18 2025 – First anomalous radioactivity intersected in drill hole PLN25‑202 (six zones over 90 m).
  • Apr 15 2025 – Discovered Tetra zone in drill hole PLN25‑205 with a 1.0 m high‑grade interval (2.50 % U₃O₈) within a 22.5 m mineralized section averaging 0.26 % U₃O₈ (384.5–407.0 m).
  • Commentary: Sam Hartmann, VP Exploration, highlighted that the new SWMLEM survey provides tighter control over conductor locations compared with earlier first‑pass surveys and is expected to reduce drilling requirements.
  • Project Overview: The Patterson Lake North (PLN) project spans 42,961 ha in the southwestern Athabasca basin, adjacent to Paladin’s Triple R and NexGen’s Arrow high‑grade uranium deposits. It comprises:
  • JR zone discovery on the 4,074 ha Patterson Lake North property.
  • Minto property (19,864 ha).
  • Broach property (19,022 ha) hosting the Tetra zone, located ~13 km south of the JR zone.
  • Qualified Person: Raymond Ashley, P.Geo., President & COO, reviewed and approved all technical information per NI 43‑101.

Notable Quotes

“This tighter survey based on 200 m spaced lines will give us greater control over local conductor locations and reduce exploration drilling.” – Sam Hartmann, Vice‑President of Exploration, F3 Uranium Corp.