EFF 0.030 +20.0% W 0.500 +1.0% RDG 0.160 +0.0% ARIC 0.780 +4.0% VROY 3.44 +5.2% ROCK 3.81 +3.0% APMI 0.120 +0.0% EM 3.58 −4.8% ALS 66.04 +6.8% MEK 0.065 +44.4% TLO 6.00 +13.0% ADE 0.045 −66.7% FAIR 0.060 +33.3% SVRS 0.420 −2.3% RES 0.050 +42.9% CYG 0.120 +0.0% EFF 0.030 +20.0% W 0.500 +1.0% RDG 0.160 +0.0% ARIC 0.780 +4.0% VROY 3.44 +5.2% ROCK 3.81 +3.0% APMI 0.120 +0.0% EM 3.58 −4.8% ALS 66.04 +6.8% MEK 0.065 +44.4% TLO 6.00 +13.0% ADE 0.045 −66.7% FAIR 0.060 +33.3% SVRS 0.420 −2.3% RES 0.050 +42.9% CYG 0.120 +0.0%
Production / Operations

Bitfarms Announces Plans for Conversion of Washington Site to HPC/AI Workloads

BITF · Price

Executive Summary

  • Bitfarms announced a fully funded $128 million agreement to convert its 18 MW Washington Bitcoin mining site into a high‑performance computing/AI data center, targeting completion in December 2026.
  • The conversion will support Nvidia GB300 GPUs with advanced liquid‑cooling and modular infrastructure, delivering up to 190 kW per rack and an industry‑leading PUE of 1.2–1.3.
  • Management highlighted that the GPU‑as‑a‑Service/Cloud monetization strategy at this site could generate net operating income exceeding historic Bitcoin mining results, providing a new cash‑flow foundation as the company winds down its mining operations in 2026‑27.

Key Details

  • Agreement: Binding, fully funded contract worth US $128 million with a large publicly traded American multinational data‑center infrastructure provider.
  • Scope of Supply: Partner will furnish all critical IT equipment and building materials for 18 MW gross capacity.
  • Performance Targets:
  • Up to 190 kW per rack power density.
  • Expected PUE (Power Usage Effectiveness) between 1.2‑1.3, indicating high energy efficiency.
  • Technology: Facility designed for Nvidia GB300 GPUs with state‑of‑the‑art liquid cooling; future focus on Nvidia “Vera Rubin” GPU generation across the portfolio.
  • Infrastructure Design: Modular construction enabling phased deployment and scalability; validated reference designs ensure compatibility and performance.
  • Timeline: Construction to begin promptly; completion targeted for December 2026.
  • Strategic Rationale:
  • Diversify away from Bitcoin mining as the company plans to wind down mining operations in 2026‑27.
  • Potentially generate higher net operating income than historic mining, supporting OPEX, G&A, debt service, and future capex.
  • Leverage nearly $1 billion in cash, unused credit facilities, Bitcoin holdings, and possible GPU financing options for the conversion.
  • Monetization Plans: Pursuing both colocation services and a GPU‑as‑a‑Service/Cloud offering at the Washington site.

Notable Quotes

“We continue executing on our HPC/AI infrastructure development strategy with a fully funded supply chain and plan to convert our Washington site to support Nvidia GB300s with state‑of‑the‑art liquid cooling,” – Ben Gagnon, Chief Executive Officer
“The conversion of just our Washington site to GPU‑as‑a‑Service could potentially produce more net operating income than we have ever generated with Bitcoin mining…” – Ben Gagnon, CEO

Read the original news release →