Production / Operations
Bitfarms Announces Plans for Conversion of Washington Site to HPC/AI Workloads

BITF · Price
Executive Summary
- Bitfarms announced a fully funded $128 million agreement to convert its 18 MW Washington Bitcoin mining site into a high‑performance computing/AI data center, targeting completion in December 2026.
- The conversion will support Nvidia GB300 GPUs with advanced liquid‑cooling and modular infrastructure, delivering up to 190 kW per rack and an industry‑leading PUE of 1.2–1.3.
- Management highlighted that the GPU‑as‑a‑Service/Cloud monetization strategy at this site could generate net operating income exceeding historic Bitcoin mining results, providing a new cash‑flow foundation as the company winds down its mining operations in 2026‑27.
Key Details
- Agreement: Binding, fully funded contract worth US $128 million with a large publicly traded American multinational data‑center infrastructure provider.
- Scope of Supply: Partner will furnish all critical IT equipment and building materials for 18 MW gross capacity.
- Performance Targets:
- Up to 190 kW per rack power density.
- Expected PUE (Power Usage Effectiveness) between 1.2‑1.3, indicating high energy efficiency.
- Technology: Facility designed for Nvidia GB300 GPUs with state‑of‑the‑art liquid cooling; future focus on Nvidia “Vera Rubin” GPU generation across the portfolio.
- Infrastructure Design: Modular construction enabling phased deployment and scalability; validated reference designs ensure compatibility and performance.
- Timeline: Construction to begin promptly; completion targeted for December 2026.
- Strategic Rationale:
- Diversify away from Bitcoin mining as the company plans to wind down mining operations in 2026‑27.
- Potentially generate higher net operating income than historic mining, supporting OPEX, G&A, debt service, and future capex.
- Leverage nearly $1 billion in cash, unused credit facilities, Bitcoin holdings, and possible GPU financing options for the conversion.
- Monetization Plans: Pursuing both colocation services and a GPU‑as‑a‑Service/Cloud offering at the Washington site.
Notable Quotes
“We continue executing on our HPC/AI infrastructure development strategy with a fully funded supply chain and plan to convert our Washington site to support Nvidia GB300s with state‑of‑the‑art liquid cooling,” – Ben Gagnon, Chief Executive Officer
“The conversion of just our Washington site to GPU‑as‑a‑Service could potentially produce more net operating income than we have ever generated with Bitcoin mining…” – Ben Gagnon, CEO
More from BITFARMS LTD. J
Apr 01, 2026 · 09:00