CAN 0.055 +0.0% NVO 0.055 +0.0% ARIS 19.57 −4.2% IVN 10.59 −0.8% MCI 0.165 +0.0% MTS 0.130 +0.0% PPX 0.210 +0.0% ICON 0.030 −33.3% ACS 0.070 +0.0% EMPR 0.860 +2.4% CYG 0.140 +0.0% IZN 0.075 +25.0% XXIX 0.110 +0.0% MERG 0.815 −4.1% LEGY 0.910 +3.4% GTWO 9.19 −3.6% CAN 0.055 +0.0% NVO 0.055 +0.0% ARIS 19.57 −4.2% IVN 10.59 −0.8% MCI 0.165 +0.0% MTS 0.130 +0.0% PPX 0.210 +0.0% ICON 0.030 −33.3% ACS 0.070 +0.0% EMPR 0.860 +2.4% CYG 0.140 +0.0% IZN 0.075 +25.0% XXIX 0.110 +0.0% MERG 0.815 −4.1% LEGY 0.910 +3.4% GTWO 9.19 −3.6%
Technical Study

ARIS MINING ANNOUNCES POSITIVE PREFEASIBILITY STUDY RESULTS FOR THE SOTO NORTE GOLD PROJECT IN COLOMBIA

ARIS · Price

Executive Summary

  • Aris Mining released a positive prefeasibility study (PFS) for its 51 % owned Soto Norte Gold Project in Colombia, confirming robust economics with an after‑tax NPV₅% of $2.7 bn (base case gold price $2,600/oz) and IRR of 35.4 %.
  • The PFS proposes a reduced processing capacity of 3,500 tpd (down from >7,000 tpd) with 750 tpd dedicated to local community miners, supporting a 22‑year mine life and a payback period of ~2.3 years.
  • Project highlights include measured & indicated resources of 39 Mt @ 5.55 g/t Au (7 Moz gold), proven & probable reserves of 20.3 Mt @ 7.00 g/t Au (4.6 Moz gold), low cash costs ($345/oz) and AISC ($534/oz), and strong by‑product credits from copper and silver.

Key Details

  • Processing Design: 3,500 tpd mill capacity; 750 tpd (≥20 % of capacity) allocated to material purchased from local community miners.
  • Resource Estimate (100 % basis):
  • Measured & Indicated: 39.0 Mt @ 5.55 g/t Au → 7.0 Moz gold, 28.2 Moz Ag, 159.2 Mlb Cu.
  • Inferred resources also disclosed (25.1 Mt @ 4.81 g/t Au).
  • Reserve Estimate (100 % basis): Proven + Probable: 20.3 Mt @ 7.00 g/t Au → 4.6 Moz gold, 20.9 Moz Ag, 89.2 Mlb Cu.
  • Economic Highlights (Base case $2,600/oz Au):
  • After‑tax NPV₅%: $2.68 bn; IRR: 35.4 %; Payback: 2.3 years.
  • Initial capital cost: $625 M (incl. pre‑production, VAT, contingency).
  • Life‑of‑mine cash cost: $345/oz Au; AISC: $534/oz Au.
  • Average annual gold production: 263 koz (years 2‑10); 203 koz (years 1‑21).
  • EBITDA: $547 M avg (years 2‑10); $410 M avg (years 1‑21).
  • Sensitivity to Gold Price: At $3,200/oz Au, NPV₅% rises to $3.56 bn and IRR to 42.1 %; payback improves to ~2.0 years.
  • Environmental & Social Features: No cyanide or mercury use; 96.5 % water recycling (net demand 2.8 L/s); tailings thickening with underground backfill; rope‑conveyor ore transport; community processing capacity; extensive water protection measures.
  • Next Steps: Completion of remaining environmental studies and filing for an environmental license in early 2026.

Notable Quotes

“The Soto Norte PFS outlines a project that balances scale, profitability, environmental stewardship, and community input… delivering significant long‑term value for shareholders and our community partners.” – Neil Woodyer, CEO, Aris Mining


All amounts are in U.S. dollars unless otherwise noted.

Read the original news release →